Larks Green Solar Farm (70 MW)

Larks Green Solar Farm is a 70 MW solar farm project in South Gloucestershire, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: operational since 2 May 2023; the record was last updated on 16 May 2023.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

70 MWsolar farm
operationalstatus in REPD
16 May 2023record last updated
South Gloucestershirecouncil area

Planning timeline

DateStage
21 August 2020Application submitted
5 January 2021Planning permission granted
1 December 2021Construction started
2 May 2023Operational

Project details

Technology
solar farm
Capacity
70 MW
Status (REPD)
operational
Record last updated
16 May 2023
Operator or applicant
Enso Energy / Iron Acton Green
Planning authority
South Gloucestershire
Planning application reference
P20/13909/F
Site area
106.0 ha
Address (REPD)
Land North and West Of Iron Acto, Iron Acton, Bristol, Avon
Council area (by location)
South Gloucestershire
Time to decision
20 weeks
REPD reference
8051

The scheme also includes 49.5 MW of battery storage, recorded separately in REPD (operational).

Who decides

ApplicationsSouth GloucestershireUK
Decided applications (solar, wind, battery)7910,236
Refused7 (9%)19%
Solar refused3 of 5912%
Onshore wind refused2 of 445%
Battery storage refused2 of 1616%
Median time from submission to decision11.1 weeks17.0 weeks
Appeals lodged / allowed3 / 1—

Other large projects within 10 km

ProjectTypeMWStatuskm
Larks Lane, Iron Actonbattery storage20application submitted0.9
Lower Larks Farmbattery storage99.9approved, not built1.0
Iron Acton Substation, Latteridge Lanebattery storage99approved, not built1.3
Patch Elm Lanebattery storage35approved, not built1.3
Larks Lane & Latteridge Lane, Latteridgebattery storage49.9approved, not built1.4
Alveston Wind Parkwind farm6.9operational1.7
Tower Hill Farmsolar farm8.1operational2.2
Green Farmsolar farm9.4refused on appeal2.3
Earthcott Green Farm, Earthcott Greenbattery storage200approved, not built2.7

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (51.5779, -2.4774).