Green Farm (9.4 MW solar farm)

Green Farm is a 9.4 MW solar farm project in South Gloucestershire, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: refused on appeal on 21 December 2015; the record was last updated on 4 January 2016.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

9.4 MWsolar farm
refused on appealstatus in REPD
4 January 2016record last updated
South Gloucestershirecouncil area

Planning timeline

DateStage
12 May 2014Application submitted
31 October 2014Refused by the planning authority
20 February 2015Appeal lodged
21 December 2015Appeal refused

Project details

Technology
solar farm
Capacity
9.4 MW
Status (REPD)
refused on appeal
Record last updated
4 January 2016
Operator or applicant
AEE Renewables
Planning authority
South Gloucestershire
Planning application reference
PK14/1755/F
Appeal reference
APP/P0119/W/15/3004513
Site area
28.5 ha
Address (REPD)
Green Farm, Folly Road, Iron Acton, South Gloucestershire
Council area (by location)
South Gloucestershire
Time to decision
25 weeks
REPD reference
2330

Who decides

ApplicationsSouth GloucestershireUK
Decided applications (solar, wind, battery)7910,236
Refused7 (9%)19%
Solar refused3 of 5912%
Onshore wind refused2 of 445%
Battery storage refused2 of 1616%
Median time from submission to decision11.1 weeks17.0 weeks
Appeals lodged / allowed3 / 1—

Other large projects within 10 km

ProjectTypeMWStatuskm
Larks Lane & Latteridge Lane, Latteridgebattery storage49.9approved, not built0.9
Iron Acton Substation, Latteridge Lanebattery storage99approved, not built1.1
Lower Larks Farmbattery storage99.9approved, not built1.3
Old Green Farm, Alveston Battery Storagebattery storage10approved, not built1.4
Elm Farm solar farm and Battery storagesolar farm24refused1.4
Larks Lane, Iron Actonbattery storage20application submitted1.4
Perrinpit Farmsolar farm49.9under construction1.6
Earthcott Green Farm, Earthcott Greenbattery storage200approved, not built1.7
Alveston Wind Parkwind farm6.9operational1.8

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (51.5585, -2.4871).