Energy Projects Near You

Lower Larks Farm (99.9 MW battery storage)

Lower Larks Farm is a 99.9 MW battery storage project in South Gloucestershire, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: approved on 14 April 2023, not yet built; the record was last updated on 15 June 2023. REPD also records that the planning permission expired on 14 April 2026, so the project may not go ahead in this form. Check the planning authority's register for the latest position.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

99.9 MWbattery storage
approved, not builtmay be out of datestatus in REPD
15 June 2023record last updated
South Gloucestershirecouncil area

REPD also records that the planning permission expired on 14 April 2026, so the project may not go ahead in this form.

Planning timeline

DateStage
20 July 2022Application submitted
14 April 2023Planning permission granted
14 April 2026Permission expired

Project details

Technology
battery storage (stand-alone storage)
Capacity
99.9 MW
Status (REPD)
approved, not built
Record last updated
15 June 2023
Operator or applicant
IPP Cero Generation
Planning authority
South Gloucestershire
Planning application reference
P22/03743/F
Address (REPD)
Lower Larks Farm Larks Lane Iron Acton
Council area (by location)
South Gloucestershire
Time to decision
38 weeks
Name in REPD
Lower Larks Farm - Battery storage
REPD reference
14076

Who decides

ApplicationsSouth GloucestershireUK
Decided applications (solar, wind, battery)7910,236
Refused7 (9%)19%
Solar refused3 of 5912%
Onshore wind refused2 of 445%
Battery storage refused2 of 1616%
Median time from submission to decision11.1 weeks17.0 weeks
Appeals lodged / allowed3 / 1—

Other large projects within 10 km

ProjectTypeMWStatuskm
Larks Lane, Iron Actonbattery storage20application submitted0.2
Larks Lane & Latteridge Lane, Latteridgebattery storage49.9approved, not built0.4
Iron Acton Substation, Latteridge Lanebattery storage99approved, not built0.4
Larks Green Solar Farmsolar farm70operational1.0
Patch Elm Lanebattery storage35approved, not built1.1
Green Farmsolar farm9.4refused on appeal1.3
Alveston Wind Parkwind farm6.9operational1.4
Earthcott Green Farm, Earthcott Greenbattery storage200approved, not built2.1
Old Green Farm, Alveston Battery Storagebattery storage10approved, not built2.1

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (51.5691, -2.4808).