Energy Projects Near You

Solar, wind and battery projects near Bristol (BS35)

64 solar, wind or battery projects of 150 kW or more are recorded within 10 km of the centre of BS35 (South Gloucestershire): 7 are waiting for a planning decision, 37 approved but not yet running, 15 operational. The largest live scheme is Earthcott Green Farm, Earthcott Green (200 MW battery storage, approved on 30 July 2025, not yet built), 4.6 km away. Source: Renewable Energy Planning Database, July 2026 extract.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

64projects within 10 km
7awaiting a decision
37approved, not running
15operational

Projects within 10 km of BS35

Projects of 1 MW and more (42)

ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updatedCouncilkm
Ingst Hill Wind Farm/ M48 Wind Farmwind farmwind farm5.2appeal withdrawnupdated Oct 2015Dec 2012refused Dec 2014Oct 2015South Gloucestershire4.2
Alveston Wind Parkwind farmwind farm6.9operationalupdated Dec 2017Jun 2008granted Nov 2008Dec 2017South Gloucestershire4.4
Parklandssolar farmsolar farm4.6operationalupdated Mar 2016May 2015granted Oct 2015Mar 2016South Gloucestershire4.5
Earthcott Green Farm, Earthcott Greenbattery storagebattery storage200approved, not builtupdated Aug 2025Mar 2023granted Jul 2025Aug 2025South Gloucestershire4.6
Old Green Farm, Alveston Battery Storagebattery storagebattery storage10approved, not built may be out of dateupdated Aug 2020Apr 2017granted Nov 2019Aug 2020South Gloucestershire5.1
Emergency Air Operation Base, Gloucester Roadsolar farmsolar farm6application submittedupdated Apr 2026Jan 2026—Apr 2026South Gloucestershire5.1
Tower Hill Farmsolar farmsolar farm8.1operationalupdated Dec 2015Jul 2014granted Oct 2014Dec 2015South Gloucestershire5.3
Larks Green Solar Farmsolar farmsolar farm70operationalupdated May 2023Aug 2020granted Jan 2021May 2023South Gloucestershire5.4
Larks Green Solar Farmbattery storagebattery storage49.5operationalupdated Nov 2024Aug 2020granted Jan 2021Nov 2024South Gloucestershire5.4
Iron Acton Substation, Latteridge Lanebattery storagebattery storage99approved, not builtupdated Sep 2024Aug 2023granted Aug 2024Sep 2024South Gloucestershire5.4
Lower Larks Farmbattery storagebattery storage99.9approved, not built may be out of dateupdated Jun 2023Jul 2022granted Apr 2023Jun 2023South Gloucestershire5.7
Stoneyard Lane Wind Farmwind farmwind farm10refused on appealupdated Jan 2012Sep 2010refused Mar 2011Jan 2012South Gloucestershire5.8
Larks Lane, Iron Actonbattery storagebattery storage20application submitted may be out of dateupdated Jun 2023May 2023—Jun 2023South Gloucestershire5.8
Larks Lane & Latteridge Lane, Latteridgebattery storagebattery storage49.9approved, not builtupdated Feb 2024Aug 2023granted Jan 2024Feb 2024South Gloucestershire5.8
Cattybrook Solar Farmsolar farmsolar farm49.9approved, not builtupdated Feb 2026Dec 2023granted Apr 2025Feb 2026South Gloucestershire5.9
Green Farmsolar farmsolar farm9.4refused on appealupdated Jan 2016May 2014refused Oct 2014Jan 2016South Gloucestershire6.1
Oakham Farmsolar farmsolar farm8operationalupdated Apr 2016May 2015granted Oct 2015Apr 2016South Gloucestershire6.1
Patch Elm Lanebattery storagebattery storage35approved, not built may be out of dateupdated Mar 2022Nov 2021granted Mar 2022Mar 2022South Gloucestershire6.6
Hammond Court Farmsolar farmsolar farm15operationalupdated Dec 2016Jul 2014granted Feb 2015Dec 2016South Gloucestershire6.6
Grange Farm (Avon)solar farmsolar farm21operationalupdated May 2015Oct 2013granted Jan 2014May 2015South Gloucestershire6.7
Perrinpit Farmsolar farmsolar farm49.9under constructionupdated Aug 2025Mar 2021granted Sep 2022Aug 2025South Gloucestershire6.8
Elm Farm solar farm and Battery storagesolar farmsolar farm24refusedupdated Mar 2021Jul 2021refused Jan 2022Mar 2021South Gloucestershire7.4
Hill Court, Tranton Lane Hill Solar Farmsolar farmsolar farm49.9approved, not built may be out of dateupdated Oct 2025Sep 2022granted Jun 2023Oct 2025South Gloucestershire7.5
Hill Court Solar farm & Battery storagebattery storagebattery storage35approved, not builtupdated Oct 2025Mar 2025granted May 2025Oct 2025South Gloucestershire7.5
The Wave Solar & Battery Developmentsolar farmsolar farm3approved, not built may be out of dateupdated May 2021Feb 2021granted Oct 2021May 2021South Gloucestershire8.0
Varley , Talbot End Farm, Cromhall Solar Farmsolar farmsolar farm25approved, not builtupdated Sep 2025Dec 2022granted Jan 2024Sep 2025South Gloucestershire8.0
Rolls Royce Filton Campus Building 185rooftop solarrooftop solar1.8operationalupdated Feb 2017Jan 2016granted Mar 2016Feb 2017South Gloucestershire8.2
Rolls Royce Filton Campus Building 184rooftop solarrooftop solar1.4operationalupdated Feb 2017Jan 2016granted Mar 2016Feb 2017South Gloucestershire8.2
Amcor Flexiblesrooftop solarrooftop solar1.7operationalupdated Apr 2016Jun 2015granted Jul 2015Apr 2016South Gloucestershire8.5
Land adjacent to Church Roadsolar farmsolar farm3.5operationalupdated Jun 2016Apr 2015granted Sep 2015Jun 2016South Gloucestershire8.5
Rag Lane Solar Farmsolar farmsolar farm49.9approved, not built may be out of dateupdated Dec 2022Jan 2021granted Dec 2021Dec 2022South Gloucestershire8.6
Sedbury Parksolar farmsolar farm5operationalupdated Apr 2015Nov 2013granted Apr 2014Apr 2015Forest of Dean8.7
Warburtons Bakery, Western Approach Distribution Parkrooftop solarrooftop solar1.4application submittedMay 2026——South Gloucestershire8.8
Central Avenue, Severn Beachrooftop solarrooftop solar1.5approved, not built may be out of dateupdated Nov 2021Jun 2021granted Aug 2021Nov 2021South Gloucestershire8.9
Tump Solar Farmsolar farmsolar farm5operationalupdated May 2017May 2015granted Aug 2015May 2017Forest of Dean8.9
Worlds End Solar Farmsolar farmsolar farm49.9application submitted may be out of dateupdated May 2021May 2021—May 2021Stroud9.1
Central Park Solar Farm & Battery Storagesolar farmsolar farm7application submittedupdated Feb 2026Jan 2026—Feb 2026South Gloucestershire9.2
Airbus UK Industrial Complexrooftop solarrooftop solar3.1approved, not builtupdated May 2024Mar 2024granted Apr 2024May 2024South Gloucestershire9.6
The Range Distribution Centre, Severn Beachrooftop solarrooftop solar2.4approved, not builtupdated Aug 2025Jun 2025granted Jul 2025Aug 2025South Gloucestershire9.7
Dominos Pizza Uk & Ireland, Central Parkrooftop solarrooftop solar1.4approved, not builtupdated Aug 2024Jun 2024granted Jul 2024Aug 2024South Gloucestershire9.9
Says Court Farm, Coalpit Heathbattery storagebattery storage50approved, not built may be out of dateupdated Aug 2022Jul 2022granted Nov 2022Aug 2022South Gloucestershire9.9
Says Court Farm solar parksolar farmsolar farm19.8operationalupdated Apr 2014Apr 2013granted Oct 2013Apr 2014South Gloucestershire9.9
Smaller schemes under 1 MW, mostly rooftop solar (22)
ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updatedCouncilkm
Quarry Road, Alveston - Micro Battery Energy Storage Systembattery storagebattery storage0.2application submittedupdated Feb 2026Jan 2026—Feb 2026South Gloucestershire0.9
Thornbury Leisure Centre, Bristol Roadrooftop solarrooftop solar0.2approved, not builtupdated Jul 2024Apr 2024granted Jun 2024Jul 2024South Gloucestershire1.4
Great Western Air Ambulance Charity, Gloucester Roadrooftop solarrooftop solar0.2approved, not builtupdated Jul 2024Apr 2024granted Jun 2024Jul 2024South Gloucestershire5.4
Oldbury Power Station Solar Photo Voltaic Arrayrooftop solarrooftop solar0.1approved, not builtupdated Jul 2023May 2023granted Jul 2023Jul 2023South Gloucestershire5.7
Cattybrook Solar Farmbattery storagebattery storage—approved, not builtupdated Feb 2026Dec 2023granted Apr 2025Feb 2026South Gloucestershire5.9
Bradley Stoke Leisure Centre, Fiddlers Wood Lanerooftop solarrooftop solar0.4approved, not builtupdated Jun 2023May 2023granted Jun 2023Jun 2023South Gloucestershire6.8
Eastwood Park, Falfield Solar Photovoltaic (PV) Panelssolar farmsolar farm0.2approved, not built may be out of dateupdated Dec 2021Dec 2021granted Jul 2023Dec 2021South Gloucestershire7.0
Elm Farm solar farm and Battery storagebattery storagebattery storage—refusedupdated Jul 2022Jul 2021refused Jan 2022Jul 2022South Gloucestershire7.4
The Wave Solar & Battery Developmentbattery storagebattery storage—approved, not built may be out of dateupdated Jan 2023Feb 2021granted Oct 2021Jan 2023South Gloucestershire8.0
Dunelm, Centaurus Roadrooftop solarrooftop solar0.2approved, not builtupdated Jul 2023Apr 2023granted May 2023Jul 2023South Gloucestershire8.3
Carshop Bristol, Bolingbroke Wayrooftop solarrooftop solar0.1approved, not builtupdated May 2023Mar 2023granted May 2023May 2023South Gloucestershire8.7
Goldcrest Wayrooftop solarrooftop solar0.7approved, not builtupdated Jul 2026Apr 2026granted May 2026Jul 2026South Gloucestershire8.7
CHEP Severnside, Goldcrest Wayrooftop solarrooftop solar0.5approved, not builtupdated May 2024Mar 2024granted May 2024May 2024South Gloucestershire8.7
Warburtons Bakery, Western Approach Distribution Parkrooftop solarrooftop solar0.9approved, not builtupdated Jun 2026Mar 2026granted Apr 2026Jun 2026South Gloucestershire8.8
Morrison Supermarket, Lysander Roadrooftop solarrooftop solar—approved, not builtupdated Dec 2022Oct 2022granted Dec 2022Dec 2022South Gloucestershire8.8
Newhouse Farm Industrial Estate, Unit 1rooftop solarrooftop solar0.3approved, not builtupdated Mar 2026Dec 2025granted Jan 2026Mar 2026Monmouthshire8.9
Cribbs Causeway, Merlin Roadrooftop solarrooftop solar0.4approved, not builtupdated Oct 2022Aug 2022granted Oct 2022Oct 2022South Gloucestershire9.1
Central Park Solar Farm & Battery Storagebattery storagebattery storage—application submittedupdated Feb 2026Jan 2026—Feb 2026South Gloucestershire9.2
Parkway Advanced Engineering Centre, New Roadrooftop solarrooftop solar—approved, not builtupdated Mar 2025Aug 2024granted Sep 2024Mar 2025South Gloucestershire9.4
Stoke Gifford Bypass, Curtis Lane - Micro Energy Storage Systembattery storagebattery storage0.2approved, not builtupdated Apr 2026Dec 2025granted Mar 2026Apr 2026South Gloucestershire9.6
The Range Distribution Centre, Central Avenuerooftop solarrooftop solar0.9approved, not builtupdated May 2024Feb 2024granted Apr 2024May 2024South Gloucestershire9.9
Berwick Drive, Almondsbury Solar Photovoltaics Panelssolar farmsolar farm0.5approved, not built may be out of dateupdated Feb 2022Jan 2022granted May 2022Feb 2022South Gloucestershire10.0

Distance from the average position of the BS35 postcodes, not from your home. Projects of 5 MW and more have their own page with dates and planning history.

By type

TypeAllPendingApprovedOperationalRefusedMW in pipeline
Solar farm2338102291
Rooftop solar221183014.9
Wind farm300110
Battery storage1631111599

MW in pipeline: pending, approved and under-construction capacity.

How South Gloucestershire decides solar, wind and battery applications

ApplicationsSouth GloucestershireUK
Decided applications (solar, wind, battery)7910,236
Refused7 (9%)19%
Solar refused3 of 5912%
Onshore wind refused2 of 445%
Battery storage refused2 of 1616%
Median time from submission to decision11.1 weeks17.0 weeks
Appeals lodged / allowed3 / 1—

All projects in South Gloucestershire

Is the status up to date?

32% of applications still shown as pending in REPD were submitted more than two years ago, and only 37% of pending records were updated in the last 12 months, so some of them may already have been decided. Near BS35, 13 projects have a status that may be out of date (pending for over two years, or approved with a permission expiry date already passed). Check the council's planning register for the latest decision.