Solar, wind and battery projects near Bristol (BS35)
64 solar, wind or battery projects of 150 kW or more are recorded within 10 km of the centre of BS35 (South Gloucestershire): 7 are waiting for a planning decision, 37 approved but not yet running, 15 operational. The largest live scheme is Earthcott Green Farm, Earthcott Green (200 MW battery storage, approved on 30 July 2025, not yet built), 4.6 km away. Source: Renewable Energy Planning Database, July 2026 extract.
Projects within 10 km of BS35
Projects of 1 MW and more (42)
| Project | Type | MW | Status (REPD) | Submitted | Decision | Record updated | Council | km |
|---|---|---|---|---|---|---|---|---|
| Ingst Hill Wind Farm/ M48 Wind Farmwind farm | wind farm | 5.2 | appeal withdrawnupdated Oct 2015 | Dec 2012 | refused Dec 2014 | Oct 2015 | South Gloucestershire | 4.2 |
| Alveston Wind Parkwind farm | wind farm | 6.9 | operationalupdated Dec 2017 | Jun 2008 | granted Nov 2008 | Dec 2017 | South Gloucestershire | 4.4 |
| Parklandssolar farm | solar farm | 4.6 | operationalupdated Mar 2016 | May 2015 | granted Oct 2015 | Mar 2016 | South Gloucestershire | 4.5 |
| Earthcott Green Farm, Earthcott Greenbattery storage | battery storage | 200 | approved, not builtupdated Aug 2025 | Mar 2023 | granted Jul 2025 | Aug 2025 | South Gloucestershire | 4.6 |
| Old Green Farm, Alveston Battery Storagebattery storage | battery storage | 10 | approved, not built may be out of dateupdated Aug 2020 | Apr 2017 | granted Nov 2019 | Aug 2020 | South Gloucestershire | 5.1 |
| Emergency Air Operation Base, Gloucester Roadsolar farm | solar farm | 6 | application submittedupdated Apr 2026 | Jan 2026 | — | Apr 2026 | South Gloucestershire | 5.1 |
| Tower Hill Farmsolar farm | solar farm | 8.1 | operationalupdated Dec 2015 | Jul 2014 | granted Oct 2014 | Dec 2015 | South Gloucestershire | 5.3 |
| Larks Green Solar Farmsolar farm | solar farm | 70 | operationalupdated May 2023 | Aug 2020 | granted Jan 2021 | May 2023 | South Gloucestershire | 5.4 |
| Larks Green Solar Farmbattery storage | battery storage | 49.5 | operationalupdated Nov 2024 | Aug 2020 | granted Jan 2021 | Nov 2024 | South Gloucestershire | 5.4 |
| Iron Acton Substation, Latteridge Lanebattery storage | battery storage | 99 | approved, not builtupdated Sep 2024 | Aug 2023 | granted Aug 2024 | Sep 2024 | South Gloucestershire | 5.4 |
| Lower Larks Farmbattery storage | battery storage | 99.9 | approved, not built may be out of dateupdated Jun 2023 | Jul 2022 | granted Apr 2023 | Jun 2023 | South Gloucestershire | 5.7 |
| Stoneyard Lane Wind Farmwind farm | wind farm | 10 | refused on appealupdated Jan 2012 | Sep 2010 | refused Mar 2011 | Jan 2012 | South Gloucestershire | 5.8 |
| Larks Lane, Iron Actonbattery storage | battery storage | 20 | application submitted may be out of dateupdated Jun 2023 | May 2023 | — | Jun 2023 | South Gloucestershire | 5.8 |
| Larks Lane & Latteridge Lane, Latteridgebattery storage | battery storage | 49.9 | approved, not builtupdated Feb 2024 | Aug 2023 | granted Jan 2024 | Feb 2024 | South Gloucestershire | 5.8 |
| Cattybrook Solar Farmsolar farm | solar farm | 49.9 | approved, not builtupdated Feb 2026 | Dec 2023 | granted Apr 2025 | Feb 2026 | South Gloucestershire | 5.9 |
| Green Farmsolar farm | solar farm | 9.4 | refused on appealupdated Jan 2016 | May 2014 | refused Oct 2014 | Jan 2016 | South Gloucestershire | 6.1 |
| Oakham Farmsolar farm | solar farm | 8 | operationalupdated Apr 2016 | May 2015 | granted Oct 2015 | Apr 2016 | South Gloucestershire | 6.1 |
| Patch Elm Lanebattery storage | battery storage | 35 | approved, not built may be out of dateupdated Mar 2022 | Nov 2021 | granted Mar 2022 | Mar 2022 | South Gloucestershire | 6.6 |
| Hammond Court Farmsolar farm | solar farm | 15 | operationalupdated Dec 2016 | Jul 2014 | granted Feb 2015 | Dec 2016 | South Gloucestershire | 6.6 |
| Grange Farm (Avon)solar farm | solar farm | 21 | operationalupdated May 2015 | Oct 2013 | granted Jan 2014 | May 2015 | South Gloucestershire | 6.7 |
| Perrinpit Farmsolar farm | solar farm | 49.9 | under constructionupdated Aug 2025 | Mar 2021 | granted Sep 2022 | Aug 2025 | South Gloucestershire | 6.8 |
| Elm Farm solar farm and Battery storagesolar farm | solar farm | 24 | refusedupdated Mar 2021 | Jul 2021 | refused Jan 2022 | Mar 2021 | South Gloucestershire | 7.4 |
| Hill Court, Tranton Lane Hill Solar Farmsolar farm | solar farm | 49.9 | approved, not built may be out of dateupdated Oct 2025 | Sep 2022 | granted Jun 2023 | Oct 2025 | South Gloucestershire | 7.5 |
| Hill Court Solar farm & Battery storagebattery storage | battery storage | 35 | approved, not builtupdated Oct 2025 | Mar 2025 | granted May 2025 | Oct 2025 | South Gloucestershire | 7.5 |
| The Wave Solar & Battery Developmentsolar farm | solar farm | 3 | approved, not built may be out of dateupdated May 2021 | Feb 2021 | granted Oct 2021 | May 2021 | South Gloucestershire | 8.0 |
| Varley , Talbot End Farm, Cromhall Solar Farmsolar farm | solar farm | 25 | approved, not builtupdated Sep 2025 | Dec 2022 | granted Jan 2024 | Sep 2025 | South Gloucestershire | 8.0 |
| Rolls Royce Filton Campus Building 185rooftop solar | rooftop solar | 1.8 | operationalupdated Feb 2017 | Jan 2016 | granted Mar 2016 | Feb 2017 | South Gloucestershire | 8.2 |
| Rolls Royce Filton Campus Building 184rooftop solar | rooftop solar | 1.4 | operationalupdated Feb 2017 | Jan 2016 | granted Mar 2016 | Feb 2017 | South Gloucestershire | 8.2 |
| Amcor Flexiblesrooftop solar | rooftop solar | 1.7 | operationalupdated Apr 2016 | Jun 2015 | granted Jul 2015 | Apr 2016 | South Gloucestershire | 8.5 |
| Land adjacent to Church Roadsolar farm | solar farm | 3.5 | operationalupdated Jun 2016 | Apr 2015 | granted Sep 2015 | Jun 2016 | South Gloucestershire | 8.5 |
| Rag Lane Solar Farmsolar farm | solar farm | 49.9 | approved, not built may be out of dateupdated Dec 2022 | Jan 2021 | granted Dec 2021 | Dec 2022 | South Gloucestershire | 8.6 |
| Sedbury Parksolar farm | solar farm | 5 | operationalupdated Apr 2015 | Nov 2013 | granted Apr 2014 | Apr 2015 | Forest of Dean | 8.7 |
| Warburtons Bakery, Western Approach Distribution Parkrooftop solar | rooftop solar | 1.4 | application submitted | May 2026 | — | — | South Gloucestershire | 8.8 |
| Central Avenue, Severn Beachrooftop solar | rooftop solar | 1.5 | approved, not built may be out of dateupdated Nov 2021 | Jun 2021 | granted Aug 2021 | Nov 2021 | South Gloucestershire | 8.9 |
| Tump Solar Farmsolar farm | solar farm | 5 | operationalupdated May 2017 | May 2015 | granted Aug 2015 | May 2017 | Forest of Dean | 8.9 |
| Worlds End Solar Farmsolar farm | solar farm | 49.9 | application submitted may be out of dateupdated May 2021 | May 2021 | — | May 2021 | Stroud | 9.1 |
| Central Park Solar Farm & Battery Storagesolar farm | solar farm | 7 | application submittedupdated Feb 2026 | Jan 2026 | — | Feb 2026 | South Gloucestershire | 9.2 |
| Airbus UK Industrial Complexrooftop solar | rooftop solar | 3.1 | approved, not builtupdated May 2024 | Mar 2024 | granted Apr 2024 | May 2024 | South Gloucestershire | 9.6 |
| The Range Distribution Centre, Severn Beachrooftop solar | rooftop solar | 2.4 | approved, not builtupdated Aug 2025 | Jun 2025 | granted Jul 2025 | Aug 2025 | South Gloucestershire | 9.7 |
| Dominos Pizza Uk & Ireland, Central Parkrooftop solar | rooftop solar | 1.4 | approved, not builtupdated Aug 2024 | Jun 2024 | granted Jul 2024 | Aug 2024 | South Gloucestershire | 9.9 |
| Says Court Farm, Coalpit Heathbattery storage | battery storage | 50 | approved, not built may be out of dateupdated Aug 2022 | Jul 2022 | granted Nov 2022 | Aug 2022 | South Gloucestershire | 9.9 |
| Says Court Farm solar parksolar farm | solar farm | 19.8 | operationalupdated Apr 2014 | Apr 2013 | granted Oct 2013 | Apr 2014 | South Gloucestershire | 9.9 |
Smaller schemes under 1 MW, mostly rooftop solar (22)
| Project | Type | MW | Status (REPD) | Submitted | Decision | Record updated | Council | km |
|---|---|---|---|---|---|---|---|---|
| Quarry Road, Alveston - Micro Battery Energy Storage Systembattery storage | battery storage | 0.2 | application submittedupdated Feb 2026 | Jan 2026 | — | Feb 2026 | South Gloucestershire | 0.9 |
| Thornbury Leisure Centre, Bristol Roadrooftop solar | rooftop solar | 0.2 | approved, not builtupdated Jul 2024 | Apr 2024 | granted Jun 2024 | Jul 2024 | South Gloucestershire | 1.4 |
| Great Western Air Ambulance Charity, Gloucester Roadrooftop solar | rooftop solar | 0.2 | approved, not builtupdated Jul 2024 | Apr 2024 | granted Jun 2024 | Jul 2024 | South Gloucestershire | 5.4 |
| Oldbury Power Station Solar Photo Voltaic Arrayrooftop solar | rooftop solar | 0.1 | approved, not builtupdated Jul 2023 | May 2023 | granted Jul 2023 | Jul 2023 | South Gloucestershire | 5.7 |
| Cattybrook Solar Farmbattery storage | battery storage | — | approved, not builtupdated Feb 2026 | Dec 2023 | granted Apr 2025 | Feb 2026 | South Gloucestershire | 5.9 |
| Bradley Stoke Leisure Centre, Fiddlers Wood Lanerooftop solar | rooftop solar | 0.4 | approved, not builtupdated Jun 2023 | May 2023 | granted Jun 2023 | Jun 2023 | South Gloucestershire | 6.8 |
| Eastwood Park, Falfield Solar Photovoltaic (PV) Panelssolar farm | solar farm | 0.2 | approved, not built may be out of dateupdated Dec 2021 | Dec 2021 | granted Jul 2023 | Dec 2021 | South Gloucestershire | 7.0 |
| Elm Farm solar farm and Battery storagebattery storage | battery storage | — | refusedupdated Jul 2022 | Jul 2021 | refused Jan 2022 | Jul 2022 | South Gloucestershire | 7.4 |
| The Wave Solar & Battery Developmentbattery storage | battery storage | — | approved, not built may be out of dateupdated Jan 2023 | Feb 2021 | granted Oct 2021 | Jan 2023 | South Gloucestershire | 8.0 |
| Dunelm, Centaurus Roadrooftop solar | rooftop solar | 0.2 | approved, not builtupdated Jul 2023 | Apr 2023 | granted May 2023 | Jul 2023 | South Gloucestershire | 8.3 |
| Carshop Bristol, Bolingbroke Wayrooftop solar | rooftop solar | 0.1 | approved, not builtupdated May 2023 | Mar 2023 | granted May 2023 | May 2023 | South Gloucestershire | 8.7 |
| Goldcrest Wayrooftop solar | rooftop solar | 0.7 | approved, not builtupdated Jul 2026 | Apr 2026 | granted May 2026 | Jul 2026 | South Gloucestershire | 8.7 |
| CHEP Severnside, Goldcrest Wayrooftop solar | rooftop solar | 0.5 | approved, not builtupdated May 2024 | Mar 2024 | granted May 2024 | May 2024 | South Gloucestershire | 8.7 |
| Warburtons Bakery, Western Approach Distribution Parkrooftop solar | rooftop solar | 0.9 | approved, not builtupdated Jun 2026 | Mar 2026 | granted Apr 2026 | Jun 2026 | South Gloucestershire | 8.8 |
| Morrison Supermarket, Lysander Roadrooftop solar | rooftop solar | — | approved, not builtupdated Dec 2022 | Oct 2022 | granted Dec 2022 | Dec 2022 | South Gloucestershire | 8.8 |
| Newhouse Farm Industrial Estate, Unit 1rooftop solar | rooftop solar | 0.3 | approved, not builtupdated Mar 2026 | Dec 2025 | granted Jan 2026 | Mar 2026 | Monmouthshire | 8.9 |
| Cribbs Causeway, Merlin Roadrooftop solar | rooftop solar | 0.4 | approved, not builtupdated Oct 2022 | Aug 2022 | granted Oct 2022 | Oct 2022 | South Gloucestershire | 9.1 |
| Central Park Solar Farm & Battery Storagebattery storage | battery storage | — | application submittedupdated Feb 2026 | Jan 2026 | — | Feb 2026 | South Gloucestershire | 9.2 |
| Parkway Advanced Engineering Centre, New Roadrooftop solar | rooftop solar | — | approved, not builtupdated Mar 2025 | Aug 2024 | granted Sep 2024 | Mar 2025 | South Gloucestershire | 9.4 |
| Stoke Gifford Bypass, Curtis Lane - Micro Energy Storage Systembattery storage | battery storage | 0.2 | approved, not builtupdated Apr 2026 | Dec 2025 | granted Mar 2026 | Apr 2026 | South Gloucestershire | 9.6 |
| The Range Distribution Centre, Central Avenuerooftop solar | rooftop solar | 0.9 | approved, not builtupdated May 2024 | Feb 2024 | granted Apr 2024 | May 2024 | South Gloucestershire | 9.9 |
| Berwick Drive, Almondsbury Solar Photovoltaics Panelssolar farm | solar farm | 0.5 | approved, not built may be out of dateupdated Feb 2022 | Jan 2022 | granted May 2022 | Feb 2022 | South Gloucestershire | 10.0 |
Distance from the average position of the BS35 postcodes, not from your home. Projects of 5 MW and more have their own page with dates and planning history.
By type
| Type | All | Pending | Approved | Operational | Refused | MW in pipeline |
|---|---|---|---|---|---|---|
| Solar farm | 23 | 3 | 8 | 10 | 2 | 291 |
| Rooftop solar | 22 | 1 | 18 | 3 | 0 | 14.9 |
| Wind farm | 3 | 0 | 0 | 1 | 1 | 0 |
| Battery storage | 16 | 3 | 11 | 1 | 1 | 599 |
MW in pipeline: pending, approved and under-construction capacity.
How South Gloucestershire decides solar, wind and battery applications
| Applications | South Gloucestershire | UK |
|---|---|---|
| Decided applications (solar, wind, battery) | 79 | 10,236 |
| Refused | 7 (9%) | 19% |
| Solar refused | 3 of 59 | 12% |
| Onshore wind refused | 2 of 4 | 45% |
| Battery storage refused | 2 of 16 | 16% |
| Median time from submission to decision | 11.1 weeks | 17.0 weeks |
| Appeals lodged / allowed | 3 / 1 | — |
All projects in South Gloucestershire
Is the status up to date?
32% of applications still shown as pending in REPD were submitted more than two years ago, and only 37% of pending records were updated in the last 12 months, so some of them may already have been decided. Near BS35, 13 projects have a status that may be out of date (pending for over two years, or approved with a permission expiry date already passed). Check the council's planning register for the latest decision.