Tump Solar Farm (5 MW)

Tump Solar Farm is a 5 MW solar farm project in Forest of Dean, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: operational since 8 March 2017; the record was last updated on 31 May 2017.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

5 MWsolar farm
operationalstatus in REPD
31 May 2017record last updated
Forest of Deancouncil area

Planning timeline

DateStage
7 May 2015Application submitted
14 August 2015Planning permission granted
8 January 2017Construction started
8 March 2017Operational

Project details

Technology
solar farm
Capacity
5 MW
Status (REPD)
operational
Record last updated
31 May 2017
Operator or applicant
Green Energy UK Direct
Planning authority
Forest of Dean
Planning application reference
P0578/15/FUL
Site area
12.8 ha
Address (REPD)
Tump Farm, Sedbury Lane, Sedbury, Chepstow, Gwent
Council area (by location)
Forest of Dean
Time to decision
14 weeks
REPD reference
1243

Who decides

ApplicationsForest of DeanUK
Decided applications (solar, wind, battery)2810,236
Refused8 (29%)19%
Solar refused7 of 2612%
Battery storage refused1 of 216%
Median time from submission to decision14.1 weeks17.0 weeks
Appeals lodged / allowed2 / 1—

Other large projects within 10 km

ProjectTypeMWStatuskm
Sedbury Parksolar farm5operational0.7
Rhewl Farmsolar farm6operational5.5
Oak Grove Farmsolar farm5.7operational6.1
Ingst Hill Wind Farm/ M48 Wind Farmwind farm5.2appeal withdrawn7.9
Southbrook Solar Farmsolar farm5operational8.0
Stoneyard Lane Wind Farmwind farm10refused on appeal8.6
Hill Court, Tranton Lane Hill Solar Farmsolar farm49.9approved, not built8.9
Hill Court Solar farm & Battery storagebattery storage35approved, not built8.9

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (51.6451, -2.653).