Sedbury Park (5 MW solar farm)

Sedbury Park is a 5 MW solar farm project in Forest of Dean, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: operational since 27 March 2015; the record was last updated on 14 April 2015.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

5 MWsolar farm
operationalstatus in REPD
14 April 2015record last updated
Forest of Deancouncil area

Planning timeline

DateStage
11 November 2013Application submitted
23 April 2014Planning permission granted
1 November 2014Construction started
27 March 2015Operational

Project details

Technology
solar farm
Capacity
5 MW
Status (REPD)
operational
Record last updated
14 April 2015
Operator or applicant
Bee Green Solar
Planning authority
Forest of Dean
Planning application reference
P1628/13/FUL
Site area
11.5 ha
Address (REPD)
E/O Sedbury Park, Sedbury, Chepstow, Gwent, NP16
Council area (by location)
Forest of Dean
Time to decision
23 weeks
REPD reference
2056

Who decides

ApplicationsForest of DeanUK
Decided applications (solar, wind, battery)2810,236
Refused8 (29%)19%
Solar refused7 of 2612%
Battery storage refused1 of 216%
Median time from submission to decision14.1 weeks17.0 weeks
Appeals lodged / allowed2 / 1—

Other large projects within 10 km

ProjectTypeMWStatuskm
Tump Solar Farmsolar farm5operational0.7
Rhewl Farmsolar farm6operational5.3
Oak Grove Farmsolar farm5.7operational5.5
Ingst Hill Wind Farm/ M48 Wind Farmwind farm5.2appeal withdrawn7.3
Southbrook Solar Farmsolar farm5operational7.4
Stoneyard Lane Wind Farmwind farm10refused on appeal8.8
Hill Court Solar farm & Battery storagebattery storage35approved, not built9.2
Hill Court, Tranton Lane Hill Solar Farmsolar farm49.9approved, not built9.2

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (51.639, -2.6551).