Ingst Hill Wind Farm/ M48 Wind Farm (5.2 MW)

Ingst Hill Wind Farm/ M48 Wind Farm is a 5.2 MW wind farm project in South Gloucestershire, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: appeal withdrawn; the record was last updated on 29 October 2015.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

5.2 MWwind farm
appeal withdrawnstatus in REPD
29 October 2015record last updated
South Gloucestershirecouncil area

Planning timeline

DateStage
5 December 2012Application submitted
17 December 2014Refused by the planning authority
27 July 2015Appeal lodged
29 October 2015Appeal withdrawn

Project details

Technology
wind farm
Capacity
5.2 MW
Status (REPD)
appeal withdrawn
Record last updated
29 October 2015
Operator or applicant
REG Windpower
Planning authority
South Gloucestershire
Planning application reference
PT12/4071/F
Appeal reference
APP/P0119/W/15/3100557
Turbines
2
Address (REPD)
Land At Valley Farm Ingst Hill Olveston Bristol South Gloucestershire
Council area (by location)
South Gloucestershire
Time to decision
106 weeks
REPD reference
4222

Who decides

ApplicationsSouth GloucestershireUK
Decided applications (solar, wind, battery)7910,236
Refused7 (9%)19%
Solar refused3 of 5912%
Onshore wind refused2 of 445%
Battery storage refused2 of 1616%
Median time from submission to decision11.1 weeks17.0 weeks
Appeals lodged / allowed3 / 1—

Other large projects within 10 km

ProjectTypeMWStatuskm
Cattybrook Solar Farmsolar farm49.9approved, not built3.3
Oakham Farmsolar farm8operational4.3
Emergency Air Operation Base, Gloucester Roadsolar farm6application submitted4.6
Central Park Solar Farm & Battery Storagesolar farm7application submitted5.4
Earthcott Green Farm, Earthcott Greenbattery storage200approved, not built6.8
Avonmouth Port IIwind farm5operational6.8
Hammond Court Farmsolar farm15operational6.9
Old Green Farm, Alveston Battery Storagebattery storage10approved, not built7.1
Severn Road, Hallenbattery storage70approved, not built7.1

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (51.5815, -2.6034).