Energy Projects Near You

Cattybrook Solar Farm (49.9 MW)

Cattybrook Solar Farm is a 49.9 MW solar farm project in South Gloucestershire, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: approved on 17 April 2025, not yet built; the record was last updated on 16 February 2026.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

49.9 MWsolar farm
approved, not builtstatus in REPD
16 February 2026record last updated
South Gloucestershirecouncil area

Planning timeline

DateStage
13 December 2023Application submitted
17 April 2025Planning permission granted

Project details

Technology
solar farm
Capacity
49.9 MW
Status (REPD)
approved, not built
Record last updated
16 February 2026
Operator or applicant
Luminous Energy Limited
Planning authority
South Gloucestershire
Planning application reference
P23/03430/F
Site area
82.8 ha
Address (REPD)
Near Boardinghouse Lane Almondsbury
Council area (by location)
South Gloucestershire
Time to decision
70 weeks
Contracts for Difference
AR7a
REPD reference
15411

The scheme also includes battery storage, recorded separately in REPD (approved, not built).

Who decides

ApplicationsSouth GloucestershireUK
Decided applications (solar, wind, battery)7910,236
Refused7 (9%)19%
Solar refused3 of 5912%
Onshore wind refused2 of 445%
Battery storage refused2 of 1616%
Median time from submission to decision11.1 weeks17.0 weeks
Appeals lodged / allowed3 / 1—

Other large projects within 10 km

ProjectTypeMWStatuskm
Oakham Farmsolar farm8operational1.2
Emergency Air Operation Base, Gloucester Roadsolar farm6application submitted2.4
Ingst Hill Wind Farm/ M48 Wind Farmwind farm5.2appeal withdrawn3.3
Central Park Solar Farm & Battery Storagesolar farm7application submitted3.9
Hammond Court Farmsolar farm15operational4.5
Grange Farm (Avon)solar farm21operational5.1
Severn Road, Hallenbattery storage70approved, not built5.4
Avonmouth Port IIwind farm5operational5.8
Unnamed battery storage (REPD 6907)battery storage20abandoned5.8

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (51.5526, -2.5932).