Energy Projects Near You

Solar, wind and battery projects near Bristol (BS10)

86 solar, wind or battery projects of 150 kW or more are recorded within 10 km of the centre of BS10 (Bristol): 7 are waiting for a planning decision, 54 approved but not yet running, 21 operational. The largest live scheme is Earthcott Green Farm, Earthcott Green (200 MW battery storage, approved on 30 July 2025, not yet built), 9.4 km away. Source: Renewable Energy Planning Database, July 2026 extract.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

86projects within 10 km
7awaiting a decision
54approved, not running
21operational

Projects within 10 km of BS10

Projects of 1 MW and more (45)

ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updatedCouncilkm
Airbus UK Industrial Complexrooftop solarrooftop solar3.1approved, not builtupdated May 2024Mar 2024granted Apr 2024May 2024South Gloucestershire2.4
Moorhouse Farm, Moorhouse Lane Solar Parksolar farmsolar farm3.8under constructionupdated Nov 2025Jan 2023granted Apr 2024Nov 2025Bristol3.3
Moorhouse Lanesolar farmsolar farm1.8operationalupdated May 2015Dec 2013granted May 2014May 2015Bristol3.3
Rolls Royce Filton Campus Building 185rooftop solarrooftop solar1.8operationalupdated Feb 2017Jan 2016granted Mar 2016Feb 2017South Gloucestershire3.3
Rolls Royce Filton Campus Building 184rooftop solarrooftop solar1.4operationalupdated Feb 2017Jan 2016granted Mar 2016Feb 2017South Gloucestershire3.3
Severn Roadbattery storagebattery storage32operationalupdated Oct 2022Oct 2017granted Feb 2018Oct 2022Bristol3.6
Lockleaze Energy Storagebattery storagebattery storage15operationalupdated Jan 2019Mar 2017—Jan 2019Bristol3.7
The Wave Solar & Battery Developmentsolar farmsolar farm3approved, not built may be out of dateupdated May 2021Feb 2021granted Oct 2021May 2021South Gloucestershire3.8
Dominos Pizza Uk & Ireland, Central Parkrooftop solarrooftop solar1.4approved, not builtupdated Aug 2024Jun 2024granted Jul 2024Aug 2024South Gloucestershire3.8
GE Crossflowsolarsolar2.5abandonedupdated Dec 2015Jul 2014granted Oct 2014Dec 2015Bristol3.9
The Range Distribution Centre, Severn Beachrooftop solarrooftop solar2.4approved, not builtupdated Aug 2025Jun 2025granted Jul 2025Aug 2025South Gloucestershire3.9
Severn Road, Hallenbattery storagebattery storage70approved, not builtupdated Mar 2025Sep 2023granted Feb 2025Mar 2025South Gloucestershire4.1
Central Avenue, Severn Beachrooftop solarrooftop solar1.5approved, not built may be out of dateupdated Nov 2021Jun 2021granted Aug 2021Nov 2021South Gloucestershire4.3
Avonmouth Wind Powerwind farmwind farm8.2operationalupdated Feb 2014Dec 2008granted Mar 2009Feb 2014Bristol4.4
Kings Weston Lanebattery storagebattery storage20approved, not builtupdated May 2026Nov 2024granted Mar 2026May 2026Bristol4.4
Central Park Solar Farm & Battery Storagesolar farmsolar farm7application submittedupdated Feb 2026Jan 2026—Feb 2026South Gloucestershire4.5
Avonmouthsolar farmsolar farm4.2operationalupdated Sep 2018Mar 2016granted Apr 2016Sep 2018Bristol4.7
Oakham Farmsolar farmsolar farm8operationalupdated Apr 2016May 2015granted Oct 2015Apr 2016South Gloucestershire4.8
Severn Road Solar Parksolar farmsolar farm1.8operationalupdated Feb 2016Dec 2014granted May 2015Feb 2016Bristol4.9
Unnamed battery storage (REPD 6907)battery storagebattery storage20abandonedupdated Mar 2019Aug 2016—Mar 2019Bristol5.0
Cattybrook Solar Farmsolar farmsolar farm49.9approved, not builtupdated Feb 2026Dec 2023granted Apr 2025Feb 2026South Gloucestershire5.2
Warburtons Bakery, Western Approach Distribution Parkrooftop solarrooftop solar1.4application submittedMay 2026——South Gloucestershire5.3
Accolade Wineswind turbinewind turbine2.5operationalupdated May 2019Apr 2017granted Sep 2017May 2019Bristol5.5
Severn Roadwind turbinewind turbine4.2operationalupdated Feb 2024Mar 2020granted Feb 2021Feb 2024Bristol5.5
Avonmouth Port IIwind farmwind farm5operationalupdated Mar 2014Aug 2008granted Jan 2009Mar 2014South Gloucestershire5.5
Amcor Flexiblesrooftop solarrooftop solar1.7operationalupdated Apr 2016Jun 2015granted Jul 2015Apr 2016South Gloucestershire6.1
Avonmouth Port - extensionwind farmwind farm9operationalupdated Jan 2015May 2010granted Oct 2010Jan 2015Bristol6.1
Emergency Air Operation Base, Gloucester Roadsolar farmsolar farm6application submittedupdated Apr 2026Jan 2026—Apr 2026South Gloucestershire6.1
Hammond Court Farmsolar farmsolar farm15operationalupdated Dec 2016Jul 2014granted Feb 2015Dec 2016South Gloucestershire6.5
Haberfield Park Farm Solar Farmsolar farmsolar farm5approved, not builtupdated Nov 2023May 2023granted Nov 2023Nov 2023North Somerset6.6
Avonmouth Portwind farmwind farm6operationalupdated Sep 2007Aug 2005granted Dec 2005Sep 2007Bristol6.6
Land adjacent to Church Roadsolar farmsolar farm3.5operationalupdated Jun 2016Apr 2015granted Sep 2015Jun 2016South Gloucestershire6.8
Parklandssolar farmsolar farm4.6operationalupdated Mar 2016May 2015granted Oct 2015Mar 2016South Gloucestershire6.9
Grange Farm (Avon)solar farmsolar farm21operationalupdated May 2015Oct 2013granted Jan 2014May 2015South Gloucestershire7.1
Etex Building Performance, Redland Avenuerooftop solarrooftop solar6.2approved, not builtupdated Jan 2025Nov 2024granted Dec 2024Jan 2025North Somerset7.2
Etex Building Performance, Redland Avenuerooftop solarrooftop solar5.9approved, not builtupdated Jan 2025Nov 2024granted Dec 2024Jan 2025North Somerset7.2
Philip Street Car Breakersbattery storagebattery storage7.2approved, not built may be out of dateupdated Jun 2023May 2020granted Jun 2020Jun 2023Bristol7.2
Feeder Roadbattery storagebattery storage20operationalupdated Jan 2024Oct 2019granted Mar 2020Jan 2024Bristol7.4
Ingst Hill Wind Farm/ M48 Wind Farmwind farmwind farm5.2appeal withdrawnupdated Oct 2015Dec 2012refused Dec 2014Oct 2015South Gloucestershire8.3
Epic Long Ashton, Phase 1 - 3 Office Buildingssolar farmsolar farm1.1under constructionupdated Mar 2026Oct 2023granted Mar 2025Mar 2026North Somerset8.3
Partfield Farmwind farmwind farm5.6application withdrawnupdated Feb 2004Oct 2000—Feb 2004South Gloucestershire8.5
Folly Brook Road, Emersons Greenrooftop solarrooftop solar1approved, not builtupdated Oct 2022Aug 2022granted Oct 2022Oct 2022South Gloucestershire8.8
Perrinpit Farmsolar farmsolar farm49.9under constructionupdated Aug 2025Mar 2021granted Sep 2022Aug 2025South Gloucestershire8.9
Old Green Farm, Alveston Battery Storagebattery storagebattery storage10approved, not built may be out of dateupdated Aug 2020Apr 2017granted Nov 2019Aug 2020South Gloucestershire9.2
Earthcott Green Farm, Earthcott Greenbattery storagebattery storage200approved, not builtupdated Aug 2025Mar 2023granted Jul 2025Aug 2025South Gloucestershire9.4
Smaller schemes under 1 MW, mostly rooftop solar (41)
ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updatedCouncilkm
Pieminister Kitchens, Charlton Roadrooftop solarrooftop solar0.2application submittedupdated Mar 2025Mar 2025—Mar 2025Bristol0.3
Lanercost Resource And Activity Centre Solar Photovoltaics Panelsrooftop solarrooftop solar—application submittedupdated Jan 2026Dec 2025—Jan 2026Bristol0.8
Cribbs Causeway, Merlin Roadrooftop solarrooftop solar0.4approved, not builtupdated Oct 2022Aug 2022granted Oct 2022Oct 2022South Gloucestershire1.8
Morrison Supermarket, Lysander Roadrooftop solarrooftop solar—approved, not builtupdated Dec 2022Oct 2022granted Dec 2022Dec 2022South Gloucestershire2.2
Berwick Drive, Almondsbury Solar Photovoltaics Panelssolar farmsolar farm0.5approved, not built may be out of dateupdated Feb 2022Jan 2022granted May 2022Feb 2022South Gloucestershire2.2
Dunelm, Centaurus Roadrooftop solarrooftop solar0.2approved, not builtupdated Jul 2023Apr 2023granted May 2023Jul 2023South Gloucestershire2.6
Carshop Bristol, Bolingbroke Wayrooftop solarrooftop solar0.1approved, not builtupdated May 2023Mar 2023granted May 2023May 2023South Gloucestershire3.3
Lockleaze Sports Centre, Bonnington Walkbattery storagebattery storage0.2approved, not builtupdated Oct 2023Feb 2023granted Oct 2023Oct 2023Bristol3.3
Bonnington Walk, Lockleaze - Micro Energy Storage Facilitybattery storagebattery storage0.2approved, not builtupdated May 2025Feb 2025granted Apr 2025May 2025Bristol3.3
Lockleaze Sports Centre, Bonnington Walk - Micro Energy Storagebattery storagebattery storage0.2approved, not builtupdated Jan 2026Oct 2025granted Dec 2025Jan 2026Bristol3.3
Abbey Wood Retail Park, Station Roadrooftop solarrooftop solar0.3approved, not builtupdated Oct 2023Sep 2023granted Oct 2023Oct 2023South Gloucestershire3.5
Abbey Wood Retail Park, Filtonrooftop solarrooftop solar0.9approved, not builtupdated Oct 2023Sep 2023granted Oct 2023Oct 2023South Gloucestershire3.5
The Wave Solar & Battery Developmentbattery storagebattery storage—approved, not built may be out of dateupdated Jan 2023Feb 2021granted Oct 2021Jan 2023South Gloucestershire3.8
Poplar Way East, Avonmouthrooftop solarrooftop solar1approved, not builtupdated Apr 2024Mar 2024granted Apr 2024Apr 2024Bristol4.0
The Range Distribution Centre, Central Avenuerooftop solarrooftop solar0.9approved, not builtupdated May 2024Feb 2024granted Apr 2024May 2024South Gloucestershire4.1
Poplar Way East, Avonmouthrooftop solarrooftop solar0.2approved, not builtupdated Aug 2025Jun 2025granted Aug 2025Aug 2025Bristol4.1
Parkway Advanced Engineering Centre, New Roadrooftop solarrooftop solar—approved, not builtupdated Mar 2025Aug 2024granted Sep 2024Mar 2025South Gloucestershire4.3
University Of West Of England, Coldharbour Lanerooftop solarrooftop solar0.6approved, not builtupdated Sep 2024Jul 2024granted Sep 2024Sep 2024South Gloucestershire4.5
Central Park Solar Farm & Battery Storagebattery storagebattery storage—application submittedupdated Feb 2026Jan 2026—Feb 2026South Gloucestershire4.5
CHEP Severnside, Goldcrest Wayrooftop solarrooftop solar0.5approved, not builtupdated May 2024Mar 2024granted May 2024May 2024South Gloucestershire4.8
Goldcrest Wayrooftop solarrooftop solar0.7approved, not builtupdated Jul 2026Apr 2026granted May 2026Jul 2026South Gloucestershire4.8
Merebank Road Solar photovoltaics equipmentrooftop solarrooftop solar0.5approved, not builtupdated Jul 2021Jun 2021granted Aug 2021Jul 2021Bristol5.0
All Saints Church, Pembroke Road - Photovoltaic Panelsrooftop solarrooftop solar—approved, not builtupdated May 2026Nov 2022granted May 2024May 2026Bristol5.0
Cattybrook Solar Farmbattery storagebattery storage—approved, not builtupdated Feb 2026Dec 2023granted Apr 2025Feb 2026South Gloucestershire5.2
Warburtons Bakery, Western Approach Distribution Parkrooftop solarrooftop solar0.9approved, not builtupdated Jun 2026Mar 2026granted Apr 2026Jun 2026South Gloucestershire5.3
Bradley Stoke Leisure Centre, Fiddlers Wood Lanerooftop solarrooftop solar0.4approved, not builtupdated Jun 2023May 2023granted Jun 2023Jun 2023South Gloucestershire5.5
St Andrews Industrial Estate, Third Wayrooftop solarrooftop solar0.3approved, not builtupdated Jul 2024May 2024granted Jul 2024Jul 2024Bristol5.5
Great Western Air Ambulance Charity, Gloucester Roadrooftop solarrooftop solar0.2approved, not builtupdated Jul 2024Apr 2024granted Jun 2024Jul 2024South Gloucestershire5.7
Stoke Gifford Bypass, Curtis Lane - Micro Energy Storage Systembattery storagebattery storage0.2approved, not builtupdated Apr 2026Dec 2025granted Mar 2026Apr 2026South Gloucestershire5.9
Cotswold House, St Philips Road - olar Panelsrooftop solarrooftop solar0.2approved, not builtupdated Jul 2024Nov 2023granted Jun 2024Jul 2024Bristol6.3
Canons Way, City Centre Solar Photovoltaics Equipmentrooftop solarrooftop solar0.2approved, not builtupdated Mar 2026Nov 2025granted Jan 2026Mar 2026Bristol6.5
Drive Vauxhall, Avon Streetbattery storagebattery storage0.6approved, not builtupdated Mar 2023Jan 2023granted Mar 2023Mar 2023Bristol6.8
Avon Meads, Hollywood Bowlrooftop solarrooftop solar0.1approved, not builtupdated Nov 2023Sep 2023granted Nov 2023Nov 2023Bristol7.5
Great Western Air Ambulance Charityrooftop solarrooftop solar0.2operationalupdated Aug 2024——Aug 2024Bristol7.6
Roper Rhodes Limited - Roof Solar PVrooftop solarrooftop solar0.8approved, not builtupdated Oct 2021Aug 2021granted Oct 2021Oct 2021North Somerset7.7
David Lloyd Leisure Plc, Ashton Roadrooftop solarrooftop solar0.7approved, not builtupdated Oct 2023Jul 2023granted Sep 2023Oct 2023Bristol7.9
Sainsburys Superstore, Regent Streetrooftop solarrooftop solar0.2application submittedJun 2026——South Gloucestershire8.6
Emerald Park, Emersons Greenrooftop solarrooftop solar0.2approved, not builtupdated May 2023Mar 2023granted May 2023May 2023South Gloucestershire9.0
David Lloyd Leisure Club, Willowherb Roadrooftop solarrooftop solar0.3approved, not builtupdated Sep 2023Jul 2023granted Sep 2023Sep 2023South Gloucestershire9.0
Iaaps, Newlands Lane Solar Panels & Hydrogen Storagerooftop solarrooftop solar0.7approved, not built may be out of dateupdated Nov 2022Sep 2022granted Oct 2022Nov 2022South Gloucestershire9.4
Sainsburys Supermarkets Limited, The Villagerooftop solarrooftop solar0.5approved, not builtupdated Apr 2024Feb 2024granted Mar 2024Apr 2024South Gloucestershire9.6

Distance from the average position of the BS10 postcodes, not from your home. Projects of 5 MW and more have their own page with dates and planning history.

By type

TypeAllPendingApprovedOperationalRefusedMW in pipeline
Solar farm172780126
Rooftop solar434354035.2
Solar100000
Wind farm600400
Wind turbine200200
Battery storage1711230309

MW in pipeline: pending, approved and under-construction capacity.

How Bristol decides solar, wind and battery applications

ApplicationsBristolUK
Decided applications (solar, wind, battery)3210,236
Refused0 (0%)19%
Solar refused0 of 1812%
Onshore wind refused0 of 645%
Battery storage refused0 of 816%
Median time from submission to decision14.1 weeks17.0 weeks
Appeals lodged / allowed0 / 0—

All projects in Bristol

Is the status up to date?

32% of applications still shown as pending in REPD were submitted more than two years ago, and only 37% of pending records were updated in the last 12 months, so some of them may already have been decided. Near BS10, 7 projects have a status that may be out of date (pending for over two years, or approved with a permission expiry date already passed). Check the council's planning register for the latest decision.