Avonmouth Port II (5 MW wind farm)

Avonmouth Port II is a 5 MW wind farm project in South Gloucestershire, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: operational since 30 September 2013; the record was last updated on 4 March 2014.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

5 MWwind farm
operationalstatus in REPD
4 March 2014record last updated
South Gloucestershirecouncil area

Planning timeline

DateStage
29 August 2008Application submitted
14 January 2009Planning permission granted
30 April 2013Construction started
30 September 2013Operational

Project details

Technology
wind farm
Capacity
5 MW
Status (REPD)
operational
Record last updated
4 March 2014
Operator or applicant
Bristol City Council - Energy Management Unit
Planning authority
Bristol, City of
Planning application reference
08/03724/FB
Turbines
2
Address (REPD)
Former Shell Tanker Site Severn Road Avonmouth Bristol
Council area (by location)
South Gloucestershire
Time to decision
20 weeks
REPD reference
3927

Who decides

ApplicationsBristolUK
Decided applications (solar, wind, battery)3210,236
Refused0 (0%)19%
Solar refused0 of 1812%
Onshore wind refused0 of 645%
Battery storage refused0 of 816%
Median time from submission to decision14.1 weeks17.0 weeks
Appeals lodged / allowed0 / 0—

Other large projects within 10 km

ProjectTypeMWStatuskm
Unnamed battery storage (REPD 6907)battery storage20abandoned0.6
Severn Road, Hallenbattery storage70approved, not built1.4
Central Park Solar Farm & Battery Storagesolar farm7application submitted1.9
Severn Roadbattery storage32operational2.4
Kings Weston Lanebattery storage20approved, not built2.6
Avonmouth Wind Powerwind farm8.2operational3.0
Avonmouth Portwind farm6operational3.5
Avonmouth Port - extensionwind farm9operational4.3
Cattybrook Solar Farmsolar farm49.9approved, not built5.8

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (51.5383, -2.6739).