Avonmouth Port - extension (9 MW wind farm)

Avonmouth Port - extension is a 9 MW wind farm project in Bristol, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: operational since 1 April 2014; the record was last updated on 5 January 2015.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

9 MWwind farm
operationalstatus in REPD
5 January 2015record last updated
Bristolcouncil area

Planning timeline

DateStage
12 May 2010Application submitted
14 October 2010Planning permission granted
5 October 2013Construction started
1 April 2014Operational

Project details

Technology
wind farm
Capacity
9 MW
Status (REPD)
operational
Record last updated
5 January 2015
Operator or applicant
Bristol Port Company
Planning authority
Bristol, City of
Planning application reference
10/02547/F
Turbines
3
Address (REPD)
St Andrews House, St Andrew's Rd, Avonmouth, Bristol, Avon
Council area (by location)
Bristol
Time to decision
22 weeks
REPD reference
4159

Who decides

ApplicationsBristolUK
Decided applications (solar, wind, battery)3210,236
Refused0 (0%)19%
Solar refused0 of 1812%
Onshore wind refused0 of 645%
Battery storage refused0 of 816%
Median time from submission to decision14.1 weeks17.0 weeks
Appeals lodged / allowed0 / 0—

Other large projects within 10 km

ProjectTypeMWStatuskm
Avonmouth Portwind farm6operational1.3
Etex Building Performance, Redland Avenuerooftop solar5.9approved, not built1.7
Etex Building Performance, Redland Avenuerooftop solar6.2approved, not built1.7
Avonmouth Wind Powerwind farm8.2operational2.0
Kings Weston Lanebattery storage20approved, not built2.2
Severn Roadbattery storage32operational3.2
Unnamed battery storage (REPD 6907)battery storage20abandoned3.8
Severn Road, Hallenbattery storage70approved, not built3.9
Avonmouth Port IIwind farm5operational4.3

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (51.5029, -2.6988).