Energy Projects Near You

Central Park Solar Farm & Battery Storage (7 MW)

Central Park Solar Farm & Battery Storage is a 7 MW solar farm project in South Gloucestershire, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: application submitted on 13 January 2026, no decision recorded; the record was last updated on 10 February 2026.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

7 MWsolar farm
application submittedstatus in REPD
10 February 2026record last updated
South Gloucestershirecouncil area

Planning timeline

DateStage
13 January 2026Application submitted

Project details

Technology
solar farm
Capacity
7 MW
Status (REPD)
application submitted
Record last updated
10 February 2026
Operator or applicant
Severnside Distribution Lane Limited
Planning authority
South Gloucestershire
Planning application reference
P26/00067/F
Site area
8.7 ha
Address (REPD)
The South Of Central Avenue Central Park Severnside
Council area (by location)
South Gloucestershire
Name in REPD
Central Park - Solar Farm & Battery Storage
REPD reference
20361

The scheme also includes battery storage, recorded separately in REPD (application submitted).

Who decides

ApplicationsSouth GloucestershireUK
Decided applications (solar, wind, battery)7910,236
Refused7 (9%)19%
Solar refused3 of 5912%
Onshore wind refused2 of 445%
Battery storage refused2 of 1616%
Median time from submission to decision11.1 weeks17.0 weeks
Appeals lodged / allowed3 / 1—

Other large projects within 10 km

ProjectTypeMWStatuskm
Severn Road, Hallenbattery storage70approved, not built1.8
Avonmouth Port IIwind farm5operational1.9
Unnamed battery storage (REPD 6907)battery storage20abandoned2.0
Severn Roadbattery storage32operational2.7
Kings Weston Lanebattery storage20approved, not built3.5
Avonmouth Wind Powerwind farm8.2operational3.8
Cattybrook Solar Farmsolar farm49.9approved, not built3.9
Oakham Farmsolar farm8operational4.6
Avonmouth Portwind farm6operational5.1

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (51.5413, -2.6461).