Oakham Farm (8 MW solar farm)

Oakham Farm is an 8 MW solar farm project in South Gloucestershire, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: operational since 22 February 2016; the record was last updated on 18 April 2016.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

8 MWsolar farm
operationalstatus in REPD
18 April 2016record last updated
South Gloucestershirecouncil area

Planning timeline

DateStage
22 May 2015Application submitted
22 October 2015Planning permission granted
18 February 2016Construction started
22 February 2016Operational

Project details

Technology
solar farm
Capacity
8 MW
Status (REPD)
operational
Record last updated
18 April 2016
Operator or applicant
Anesco/Parklands Solar
Planning authority
South Gloucestershire
Planning application reference
PT15/2164/F
Site area
8.7 ha
Address (REPD)
Oakham Farm Land At Parklands Almondsbury Bristol South Gloucestershire
Council area (by location)
South Gloucestershire
Time to decision
22 weeks
REPD reference
1269

Who decides

ApplicationsSouth GloucestershireUK
Decided applications (solar, wind, battery)7910,236
Refused7 (9%)19%
Solar refused3 of 5912%
Onshore wind refused2 of 445%
Battery storage refused2 of 1616%
Median time from submission to decision11.1 weeks17.0 weeks
Appeals lodged / allowed3 / 1—

Other large projects within 10 km

ProjectTypeMWStatuskm
Cattybrook Solar Farmsolar farm49.9approved, not built1.2
Emergency Air Operation Base, Gloucester Roadsolar farm6application submitted1.6
Hammond Court Farmsolar farm15operational3.4
Grange Farm (Avon)solar farm21operational4.0
Ingst Hill Wind Farm/ M48 Wind Farmwind farm5.2appeal withdrawn4.3
Central Park Solar Farm & Battery Storagesolar farm7application submitted4.6
Earthcott Green Farm, Earthcott Greenbattery storage200approved, not built5.2
Old Green Farm, Alveston Battery Storagebattery storage10approved, not built5.2
Perrinpit Farmsolar farm49.9under construction5.7

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (51.5458, -2.5796).