Grange Farm (Avon) (21 MW solar farm)

Grange Farm (Avon) is a 21 MW solar farm project in South Gloucestershire, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: operational since 11 December 2014; the record was last updated on 29 May 2015.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

21 MWsolar farm
operationalstatus in REPD
29 May 2015record last updated
South Gloucestershirecouncil area

Planning timeline

DateStage
17 October 2013Application submitted
6 January 2014Planning permission granted
1 September 2014Construction started
11 December 2014Operational

Project details

Technology
solar farm
Capacity
21 MW
Status (REPD)
operational
Record last updated
29 May 2015
Operator or applicant
Solar Power South
Planning authority
South Gloucestershire
Planning application reference
PT13/3662/F
Site area
37.0 ha
Address (REPD)
Grange Farm, Old Gloucester Road, Winterbourne, Bristol, South Gloucestershire
Council area (by location)
South Gloucestershire
Time to decision
12 weeks
REPD reference
1914

Who decides

ApplicationsSouth GloucestershireUK
Decided applications (solar, wind, battery)7910,236
Refused7 (9%)19%
Solar refused3 of 5912%
Onshore wind refused2 of 445%
Battery storage refused2 of 1616%
Median time from submission to decision11.1 weeks17.0 weeks
Appeals lodged / allowed3 / 1—

Other large projects within 10 km

ProjectTypeMWStatuskm
Hammond Court Farmsolar farm15operational0.6
Perrinpit Farmsolar farm49.9under construction1.9
Old Green Farm, Alveston Battery Storagebattery storage10approved, not built2.5
Emergency Air Operation Base, Gloucester Roadsolar farm6application submitted2.8
Earthcott Green Farm, Earthcott Greenbattery storage200approved, not built2.8
Green Farmsolar farm9.4refused on appeal3.2
Elm Farm solar farm and Battery storagesolar farm24refused3.3
Alveston Wind Parkwind farm6.9operational4.0
Oakham Farmsolar farm8operational4.0

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (51.5397, -2.5227).