Elm Farm solar farm and Battery storage (24 MW)

Elm Farm solar farm and Battery storage is a 24 MW solar farm project in South Gloucestershire, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: refused on 28 January 2022; the record was last updated on 4 March 2021.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

24 MWsolar farm
refusedstatus in REPD
4 March 2021record last updated
South Gloucestershirecouncil area

Planning timeline

DateStage
5 July 2021Application submitted
28 January 2022Refused by the planning authority

Project details

Technology
solar farm
Capacity
24 MW
Status (REPD)
refused
Record last updated
4 March 2021
Operator or applicant
Enso Energy Limited
Planning authority
South Gloucestershire
Planning application reference
P21/04721/F
Site area
38.0 ha
Address (REPD)
Land At Elm Farm Bristol Road Iron Acton
Council area (by location)
South Gloucestershire
Time to decision
30 weeks
REPD reference
8486

The scheme also includes battery storage, recorded separately in REPD (refused).

Who decides

ApplicationsSouth GloucestershireUK
Decided applications (solar, wind, battery)7910,236
Refused7 (9%)19%
Solar refused3 of 5912%
Onshore wind refused2 of 445%
Battery storage refused2 of 1616%
Median time from submission to decision11.1 weeks17.0 weeks
Appeals lodged / allowed3 / 1—

Other large projects within 10 km

ProjectTypeMWStatuskm
Green Farmsolar farm9.4refused on appeal1.4
Perrinpit Farmsolar farm49.9under construction1.4
Larks Lane & Latteridge Lane, Latteridgebattery storage49.9approved, not built2.0
Iron Acton Substation, Latteridge Lanebattery storage99approved, not built2.3
Lower Larks Farmbattery storage99.9approved, not built2.4
Old Green Farm, Alveston Battery Storagebattery storage10approved, not built2.5
Larks Lane, Iron Actonbattery storage20application submitted2.5
Says Court Farm, Coalpit Heathbattery storage50approved, not built2.5
Says Court Farm solar parksolar farm19.8operational2.5

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (51.5478, -2.4769).