Haberfield Park Farm Solar Farm (5 MW)

Haberfield Park Farm Solar Farm is a 5 MW solar farm project in North Somerset, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: approved on 17 November 2023, not yet built; the record was last updated on 21 November 2023.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

5 MWsolar farm
approved, not builtstatus in REPD
21 November 2023record last updated
North Somersetcouncil area

Planning timeline

DateStage
23 May 2023Application submitted
17 November 2023Planning permission granted
17 November 2026Permission due to expire (unless work starts)

Project details

Technology
solar farm
Capacity
5 MW
Status (REPD)
approved, not built
Record last updated
21 November 2023
Operator or applicant
PS Renewables Limited
Planning authority
North Somerset
Planning application reference
23/P/1061/FUL
Site area
7.8 ha
Address (REPD)
Haberfield Park Farm, Pill Road, Bristol
Council area (by location)
North Somerset
Time to decision
25 weeks
Name in REPD
Haberfield Park Farm - Solar Farm
REPD reference
14017

Who decides

ApplicationsNorth SomersetUK
Decided applications (solar, wind, battery)4910,236
Refused7 (14%)19%
Solar refused2 of 3812%
Onshore wind refused0 of 145%
Battery storage refused5 of 1016%
Median time from submission to decision14.4 weeks17.0 weeks
Appeals lodged / allowed0 / 2—

Other large projects within 10 km

ProjectTypeMWStatuskm
Etex Building Performance, Redland Avenuerooftop solar5.9approved, not built3.6
Etex Building Performance, Redland Avenuerooftop solar6.2approved, not built3.6
Avonmouth Port - extensionwind farm9operational4.4
Avonmouth Wind Powerwind farm8.2operational5.2
Kings Weston Lanebattery storage20approved, not built5.5
Avonmouth Portwind farm6operational5.8
Severn Roadbattery storage32operational6.0
Severn Road, Hallenbattery storage70approved, not built7.1
Unnamed battery storage (REPD 6907)battery storage20abandoned7.5

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (51.4652, -2.6772).