Energy Projects Near You

Renewable energy projects in North Somerset

57 solar, wind or battery projects of 150 kW or more are located in North Somerset (REPD, July 2026 extract): 8 pending, 33 approved but not running, 8 operational and 7 refused. The council refused 7 of 49 decided applications (14%; UK 19%), with a median 14 weeks from submission to decision.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

57projects in the council area
8awaiting a decision
33approved, not running
14%of decisions refused

How North Somerset decides

ApplicationsNorth SomersetUK
Decided applications (solar, wind, battery)4910,236
Refused7 (14%)19%
Solar refused2 of 3812%
Onshore wind refused0 of 145%
Battery storage refused5 of 1016%
Median time from submission to decision14.4 weeks17.0 weeks
Appeals lodged / allowed0 / 2—

Projects in North Somerset

Projects of 1 MW and more (33)

ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updated
Station Road & Nye Road, Sandfordbattery storagebattery storage100application submittedupdated Aug 2025Jun 2025—Aug 2025
Yew Tree Farm, Yew Tree Lane Solar Farmsolar farmsolar farm50approved, not builtupdated Nov 2025Jul 2025granted Oct 2025Nov 2025
Yanel Farm, Churchill Green Solar Farmsolar farmsolar farm49.9approved, not builtupdated Apr 2026Jul 2022granted Apr 2024Apr 2026
Manor Farm, Wick Lane Solar Farm & Battery Storagesolar farmsolar farm49.9application submittedupdated Feb 2026Jan 2026—Feb 2026
Yeowood Farmbattery storagebattery storage49.9refusedupdated Jan 2025Aug 2024refused Dec 2024Jan 2025
The Strawberry Line, Brinsea Road Solar Farmsolar farmsolar farm49.9approved, not builtupdated Feb 2026Apr 2025granted Aug 2025Feb 2026
Oldbridge, Congresbury Solar Farmsolar farmsolar farm40application submittedupdated Jun 2026Jun 2025—Jun 2026
Kitland Solar Farmsolar farmsolar farm40approved, not builtupdated Feb 2026May 2024granted Dec 2024Feb 2026
Brinsea Green Farm, Brinsea Lanesolar farmsolar farm30approved, not builtupdated Feb 2026Oct 2023granted Feb 2025Feb 2026
Sandbay, Elmsley Lane, Kewstoke Solar Farmsolar farmsolar farm24.5approved, not builtupdated Feb 2026Feb 2023granted Oct 2024Feb 2026
Manor Farm, Wick Lane Solar Farm & Battery Storagebattery storagebattery storage24application submittedupdated Feb 2026Jan 2026—Feb 2026
Bowerhouse Farm (extension)solar farmsolar farm19.8under constructionupdated Nov 2021Mar 2020granted Mar 2022Nov 2021
East Dundry Lane, Norton Hawkfield Solar Farmsolar farmsolar farm15application submittedupdated Dec 2025Jul 2025—Dec 2025
Howgrove Farm, Green Lanesolar farmsolar farm10approved, not builtupdated Dec 2025May 2025granted Nov 2025Dec 2025
Green Lane, Nempnett Thrubwell Solar Farmsolar farmsolar farm9.1approved, not built may be out of dateupdated Jul 2025Feb 2022granted Oct 2022Jul 2025
Bowerhouse Farmsolar farmsolar farm8.3operationalupdated Oct 2015Jul 2014granted Oct 2014Oct 2015
Iwood Lane Solar Farmsolar farmsolar farm8operationalupdated Jun 2015Dec 2013granted May 2014Jun 2015
The Grangesolar farmsolar farm8operationalupdated Jan 2017Sep 2014granted Feb 2015Jan 2017
South Hill Farm solar parksolar farmsolar farm7.8refusedupdated Sep 2013May 2013refused Aug 2013Sep 2013
Towerbrook Farm (Banwell Solar Farm)solar farmsolar farm7.2operationalupdated Dec 2015Aug 2014granted Nov 2014Dec 2015
Congresbury Solar Farmsolar farmsolar farm7.1operationalupdated Mar 2016Jun 2014granted Nov 2014Mar 2016
Etex Building Performance, Redland Avenuerooftop solarrooftop solar6.2approved, not builtupdated Jan 2025Nov 2024granted Dec 2024Jan 2025
Etex Building Performance, Redland Avenuerooftop solarrooftop solar5.9approved, not builtupdated Jan 2025Nov 2024granted Dec 2024Jan 2025
Garleys Wood Solar Parksolar farmsolar farm5refusedupdated Dec 2013Sep 2012refused Dec 2012Dec 2013
Land at New Orchard Farmsolar farmsolar farm5permission expiredupdated Apr 2019Oct 2014granted Jun 2015Apr 2019
Haberfield Park Farm Solar Farmsolar farmsolar farm5approved, not builtupdated Nov 2023May 2023granted Nov 2023Nov 2023
Howgrove Farmsolar farmsolar farm4.7refused on appealupdated Mar 2016Sep 2014refused Jun 2015Mar 2016
Smart Systems Limited, Arnolds Wayrooftop solarrooftop solar2.9under constructionupdated Nov 2023Jul 2023granted Oct 2023Nov 2023
Epic Long Ashton, Phase 1 - 3 Office Buildingssolar farmsolar farm1.1under constructionupdated Mar 2026Oct 2023granted Mar 2025Mar 2026
Twin Elm Solar Farmsolar farmsolar farm1operationalupdated Dec 2013Mar 2012granted Jun 2012Dec 2013
Smart Systemsrooftop solarrooftop solar1approved, not built may be out of dateupdated Jun 2019Apr 2015granted Sep 2015Jun 2019
Smart Systemswind farmwind farm1approved, not built may be out of dateupdated Mar 2020Apr 2015granted Sep 2015Mar 2020
Lag Farmrooftop solarrooftop solar1operationalupdated Jun 2020Dec 2019granted Jan 2020Jun 2020
Smaller schemes under 1 MW, mostly rooftop solar (24)
ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updated
Arnolds Way, Yattonrooftop solarrooftop solar0.8under constructionupdated Mar 2022Feb 2022granted Oct 2022Mar 2022
Roper Rhodes Limited - Roof Solar PVrooftop solarrooftop solar0.8approved, not builtupdated Oct 2021Aug 2021granted Oct 2021Oct 2021
Langford - Roof Mounted Solar Photovoltaic Panelsrooftop solarrooftop solar0.6approved, not builtupdated Mar 2022Mar 2022granted Apr 2022Mar 2022
Cadbury Garden And Leisurerooftop solarrooftop solar0.5approved, not builtupdated Dec 2021Oct 2021granted Nov 2021Dec 2021
Weston College University Campus, Loxton Road - Air Source Heat Pumpsrooftop solarrooftop solar0.4approved, not builtupdated May 2025Feb 2025granted Apr 2025May 2025
Morrisons, Worle Moor Gaterooftop solarrooftop solar0.3approved, not builtupdated Apr 2024Jan 2024granted Mar 2024Apr 2024
Bournville Primary School, Selworthy Roadrooftop solarrooftop solar0.3approved, not builtupdated Jan 2026Sep 2025granted Dec 2025Jan 2026
Weston Collegerooftop solarrooftop solar0.3approved, not builtupdated Apr 2025Jan 2025granted Apr 2025Apr 2025
Lower Strode Roadrooftop solarrooftop solar0.3approved, not builtupdated Jul 2022Jul 2022granted Aug 2022Jul 2022
Coles Quarry, Church Townbattery storagebattery storage0.2refusedupdated Apr 2025Dec 2024refused Apr 2025Apr 2025
Westbury Crescent, Loxton Road - Micro Energy Storage Facilitybattery storagebattery storage0.2approved, not builtupdated Apr 2026Mar 2025granted Feb 2026Apr 2026
Weston Youth Centre, Coleridge Roadbattery storagebattery storage0.2approved, not builtupdated Apr 2026Mar 2025granted Feb 2026Apr 2026
Weston Fire Station, Summerlands Road - Micro Energy Storagebattery storagebattery storage0.2refusedupdated Jun 2025Apr 2025refused Jun 2025Jun 2025
Recreation Ground Car Park, Strode Road - Micro Energy Storagebattery storagebattery storage0.2refusedupdated Jun 2025Apr 2025refused Jun 2025Jun 2025
Bransby Way, Heron Moor School - Micro Energy Storage Facilitybattery storagebattery storage0.2application submittedupdated May 2026Apr 2026—May 2026
Coleman Building, Portisheadrooftop solarrooftop solar0.1approved, not builtupdated Jan 2025Oct 2024granted Jan 2025Jan 2025
Nailsea Rescue Centre, Nailsearooftop solarrooftop solar—operationalupdated May 2021May 2021granted Aug 2021May 2021
Weston General Hospital - Photovoltaic Installation Projectrooftop solarrooftop solar—application submitted may be out of dateupdated Aug 2021Aug 2021—Aug 2021
Sewage Treatment Works, Warth Lanesolar farmsolar farm—approved, not builtupdated Nov 2023Oct 2023granted Nov 2023Nov 2023
Bristol Airport Solar Farmsolar farmsolar farm—under constructionupdated May 2023——May 2023
Brinsea Green Farm, Brinsea Lanebattery storagebattery storage—approved, not builtupdated Feb 2026Oct 2023granted Feb 2025Feb 2026
Lower Stock Farm, Langfordbattery storagebattery storage—approved, not builtupdated Feb 2026May 2024granted Dec 2024Feb 2026
The Strawberry Line, Brinsea Roadbattery storagebattery storage—approved, not builtupdated Feb 2026Apr 2025granted Aug 2025Feb 2026
East Dundry Lane, Norton Hawsfield Solar Farmsolar farmsolar farm—application submittedupdated Sep 2025Jul 2025—Sep 2025

Postcode districts in North Somerset

DistrictProjects within 10 kmPendingApprovedOperational
BS203501912
BS21273155
BS22396217
BS23245115
BS24426228
BS25415228
BS29486279
BS40327174
BS41365226
BS48413266
BS49415237

32% of applications still shown as pending in REPD were submitted more than two years ago, and only 37% of pending records were updated in the last 12 months, so some of them may already have been decided. Projects belong to North Somerset by location (nearest postcode to the REPD grid reference); decisions are counted by the planning authority named in REPD.