Station Road & Nye Road, Sandford (100 MW battery storage)

Station Road & Nye Road, Sandford is a 100 MW battery storage project in North Somerset, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: application submitted on 12 June 2025, no decision recorded; the record was last updated on 11 August 2025.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

100 MWbattery storage
application submittedstatus in REPD
11 August 2025record last updated
North Somersetcouncil area

Planning timeline

DateStage
12 June 2025Application submitted

Project details

Technology
battery storage (stand-alone storage)
Capacity
100 MW
Status (REPD)
application submitted
Record last updated
11 August 2025
Operator or applicant
Aura Power Developments Limited
Planning authority
North Somerset
Planning application reference
25/P/1113/FUL
Address (REPD)
North Of Station Road And West Of Nye Road Sandford
Council area (by location)
North Somerset
Name in REPD
Station Road & Nye Road, Sandford - Battery Energy Storage System
REPD reference
19207

Who decides

ApplicationsNorth SomersetUK
Decided applications (solar, wind, battery)4910,236
Refused7 (14%)19%
Solar refused2 of 3812%
Onshore wind refused0 of 145%
Battery storage refused5 of 1016%
Median time from submission to decision14.4 weeks17.0 weeks
Appeals lodged / allowed0 / 2—

Other large projects within 10 km

ProjectTypeMWStatuskm
Yanel Farm, Churchill Green Solar Farmsolar farm49.9approved, not built0.5
Towerbrook Farm (Banwell Solar Farm)solar farm7.2operational1.5
Congresbury Solar Farmsolar farm7.1operational1.8
Bowerhouse Farmsolar farm8.3operational2.2
Bowerhouse Farm (extension)solar farm19.8under construction2.6
Brinsea Green Farm, Brinsea Lanesolar farm30approved, not built3.3
The Strawberry Line, Brinsea Road Solar Farmsolar farm49.9approved, not built3.6
Iwood Lane Solar Farmsolar farm8operational4.0
Land at New Orchard Farmsolar farm5permission expired4.2

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (51.3352, -2.8339).