Iwood Lane Solar Farm (8 MW)

Iwood Lane Solar Farm is an 8 MW solar farm project in North Somerset, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: operational since 19 December 2014; the record was last updated on 19 June 2015.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

8 MWsolar farm
operationalstatus in REPD
19 June 2015record last updated
North Somersetcouncil area

Planning timeline

DateStage
12 December 2013Application submitted
14 May 2014Planning permission granted
19 December 2014Operational

Project details

Technology
solar farm
Capacity
8 MW
Status (REPD)
operational
Record last updated
19 June 2015
Operator or applicant
Wessex Solar Energy
Planning authority
North Somerset
Planning application reference
13/P/2382/F
Address (REPD)
Fields off Stock Lane and Iwood Lane, near Congresbury
Council area (by location)
North Somerset
Time to decision
22 weeks
REPD reference
1886

Who decides

ApplicationsNorth SomersetUK
Decided applications (solar, wind, battery)4910,236
Refused7 (14%)19%
Solar refused2 of 3812%
Onshore wind refused0 of 145%
Battery storage refused5 of 1016%
Median time from submission to decision14.4 weeks17.0 weeks
Appeals lodged / allowed0 / 2—

Other large projects within 10 km

ProjectTypeMWStatuskm
Yeowood Farmbattery storage49.9refused0.3
Brinsea Green Farm, Brinsea Lanesolar farm30approved, not built0.8
The Strawberry Line, Brinsea Road Solar Farmsolar farm49.9approved, not built1.2
Kitland Solar Farmsolar farm40approved, not built1.7
Oldbridge, Congresbury Solar Farmsolar farm40application submitted1.8
Congresbury Solar Farmsolar farm7.1operational2.5
Yanel Farm, Churchill Green Solar Farmsolar farm49.9approved, not built3.6
Station Road & Nye Road, Sandfordbattery storage100application submitted4.0
Land at New Orchard Farmsolar farm5permission expired4.4

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (51.3593, -2.7913).