Energy Projects Near You

Solar, wind and battery projects near Clevedon (BS21)

27 solar, wind or battery projects of 150 kW or more are recorded within 10 km of the centre of BS21 (North Somerset): 3 are waiting for a planning decision, 15 approved but not yet running, 5 operational. The largest live scheme is Yew Tree Farm, Yew Tree Lane Solar Farm (50 MW solar farm, approved on 8 October 2025, not yet built), 4.7 km away. Source: Renewable Energy Planning Database, July 2026 extract.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

27projects within 10 km
3awaiting a decision
15approved, not running
5operational

Projects within 10 km of BS21

Projects of 1 MW and more (17)

ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updatedCouncilkm
Yew Tree Farm, Yew Tree Lane Solar Farmsolar farmsolar farm50approved, not builtupdated Nov 2025Jul 2025granted Oct 2025Nov 2025North Somerset4.7
Smart Systems Limited, Arnolds Wayrooftop solarrooftop solar2.9under constructionupdated Nov 2023Jul 2023granted Oct 2023Nov 2023North Somerset4.8
Smart Systemsrooftop solarrooftop solar1approved, not built may be out of dateupdated Jun 2019Apr 2015granted Sep 2015Jun 2019North Somerset4.8
Smart Systemswind farmwind farm1approved, not built may be out of dateupdated Mar 2020Apr 2015granted Sep 2015Mar 2020North Somerset4.8
Land at New Orchard Farmsolar farmsolar farm5permission expiredupdated Apr 2019Oct 2014granted Jun 2015Apr 2019North Somerset7.1
The Grangesolar farmsolar farm8operationalupdated Jan 2017Sep 2014granted Feb 2015Jan 2017North Somerset7.2
Manor Farm, Wick Lane Solar Farm & Battery Storagesolar farmsolar farm49.9application submittedupdated Feb 2026Jan 2026—Feb 2026North Somerset7.3
Manor Farm, Wick Lane Solar Farm & Battery Storagebattery storagebattery storage24application submittedupdated Feb 2026Jan 2026—Feb 2026North Somerset7.3
Oldbridge, Congresbury Solar Farmsolar farmsolar farm40application submittedupdated Jun 2026Jun 2025—Jun 2026North Somerset7.6
The Strawberry Line, Brinsea Road Solar Farmsolar farmsolar farm49.9approved, not builtupdated Feb 2026Apr 2025granted Aug 2025Feb 2026North Somerset8.5
Bowerhouse Farm (extension)solar farmsolar farm19.8under constructionupdated Nov 2021Mar 2020granted Mar 2022Nov 2021North Somerset9.2
Iwood Lane Solar Farmsolar farmsolar farm8operationalupdated Jun 2015Dec 2013granted May 2014Jun 2015North Somerset9.3
Twin Elm Solar Farmsolar farmsolar farm1operationalupdated Dec 2013Mar 2012granted Jun 2012Dec 2013North Somerset9.3
Yeowood Farmbattery storagebattery storage49.9refusedupdated Jan 2025Aug 2024refused Dec 2024Jan 2025North Somerset9.5
Sandbay, Elmsley Lane, Kewstoke Solar Farmsolar farmsolar farm24.5approved, not builtupdated Feb 2026Feb 2023granted Oct 2024Feb 2026North Somerset9.6
Congresbury Solar Farmsolar farmsolar farm7.1operationalupdated Mar 2016Jun 2014granted Nov 2014Mar 2016North Somerset9.6
Brinsea Green Farm, Brinsea Lanesolar farmsolar farm30approved, not builtupdated Feb 2026Oct 2023granted Feb 2025Feb 2026North Somerset9.8
Smaller schemes under 1 MW, mostly rooftop solar (10)
ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updatedCouncilkm
Recreation Ground Car Park, Strode Road - Micro Energy Storagebattery storagebattery storage0.2refusedupdated Jun 2025Apr 2025refused Jun 2025Jun 2025North Somerset1.2
Lower Strode Roadrooftop solarrooftop solar0.3approved, not builtupdated Jul 2022Jul 2022granted Aug 2022Jul 2022North Somerset2.0
Arnolds Way, Yattonrooftop solarrooftop solar0.8under constructionupdated Mar 2022Feb 2022granted Oct 2022Mar 2022North Somerset5.0
Nailsea Rescue Centre, Nailsearooftop solarrooftop solar—operationalupdated May 2021May 2021granted Aug 2021May 2021North Somerset6.0
Sewage Treatment Works, Warth Lanesolar farmsolar farm—approved, not builtupdated Nov 2023Oct 2023granted Nov 2023Nov 2023North Somerset7.1
Cadbury Garden And Leisurerooftop solarrooftop solar0.5approved, not builtupdated Dec 2021Oct 2021granted Nov 2021Dec 2021North Somerset7.2
Coleman Building, Portisheadrooftop solarrooftop solar0.1approved, not builtupdated Jan 2025Oct 2024granted Jan 2025Jan 2025North Somerset8.2
The Strawberry Line, Brinsea Roadbattery storagebattery storage—approved, not builtupdated Feb 2026Apr 2025granted Aug 2025Feb 2026North Somerset8.5
Coles Quarry, Church Townbattery storagebattery storage0.2refusedupdated Apr 2025Dec 2024refused Apr 2025Apr 2025North Somerset8.5
Brinsea Green Farm, Brinsea Lanebattery storagebattery storage—approved, not builtupdated Feb 2026Oct 2023granted Feb 2025Feb 2026North Somerset9.8

Distance from the average position of the BS21 postcodes, not from your home. Projects of 5 MW and more have their own page with dates and planning history.

By type

TypeAllPendingApprovedOperationalRefusedMW in pipeline
Solar farm132640264
Rooftop solar706105.7
Wind farm101001
Battery storage6120324

MW in pipeline: pending, approved and under-construction capacity.

How North Somerset decides solar, wind and battery applications

ApplicationsNorth SomersetUK
Decided applications (solar, wind, battery)4910,236
Refused7 (14%)19%
Solar refused2 of 3812%
Onshore wind refused0 of 145%
Battery storage refused5 of 1016%
Median time from submission to decision14.4 weeks17.0 weeks
Appeals lodged / allowed0 / 2—

All projects in North Somerset

Is the status up to date?

32% of applications still shown as pending in REPD were submitted more than two years ago, and only 37% of pending records were updated in the last 12 months, so some of them may already have been decided. Near BS21, 2 projects have a status that may be out of date (pending for over two years, or approved with a permission expiry date already passed). Check the council's planning register for the latest decision.