Sandbay, Elmsley Lane, Kewstoke Solar Farm (24.5 MW)

Sandbay, Elmsley Lane, Kewstoke Solar Farm is a 24.5 MW solar farm project in North Somerset, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: approved on 3 October 2024, not yet built; the record was last updated on 20 February 2026.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

24.5 MWsolar farm
approved, not builtstatus in REPD
20 February 2026record last updated
North Somersetcouncil area

Planning timeline

DateStage
14 February 2023Application submitted
3 October 2024Planning permission granted

Project details

Technology
solar farm
Capacity
24.5 MW
Status (REPD)
approved, not built
Record last updated
20 February 2026
Operator or applicant
Solar Southwest
Planning authority
North Somerset
Planning application reference
22/P/3036/FUL
Site area
27.0 ha
Address (REPD)
Elmsley Lane Kewstoke
Council area (by location)
North Somerset
Time to decision
85 weeks
Contracts for Difference
AR7a
Name in REPD
Sandbay, Elmsley Lane, Kewstoke - Solar Farm
REPD reference
13293

Who decides

ApplicationsNorth SomersetUK
Decided applications (solar, wind, battery)4910,236
Refused7 (14%)19%
Solar refused2 of 3812%
Onshore wind refused0 of 145%
Battery storage refused5 of 1016%
Median time from submission to decision14.4 weeks17.0 weeks
Appeals lodged / allowed0 / 2—

Other large projects within 10 km

ProjectTypeMWStatuskm
Manor Farm, Wick Lane Solar Farm & Battery Storagesolar farm49.9application submitted4.7
The Grangesolar farm8operational4.9
Yew Tree Farm, Yew Tree Lane Solar Farmsolar farm50approved, not built6.0
Bowerhouse Farm (extension)solar farm19.8under construction6.5
Land at New Orchard Farmsolar farm5permission expired6.6
Bowerhouse Farmsolar farm8.3operational6.8
South Hill Farm solar parksolar farm7.8refused7.3
Towerbrook Farm (Banwell Solar Farm)solar farm7.2operational8.0
Congresbury Solar Farmsolar farm7.1operational8.9

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (51.3739, -2.947).