Bowerhouse Farm (8.3 MW solar farm)

Bowerhouse Farm is an 8.3 MW solar farm project in North Somerset, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: operational since 29 March 2015; the record was last updated on 5 October 2015.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

8.3 MWsolar farm
operationalstatus in REPD
5 October 2015record last updated
North Somersetcouncil area

Planning timeline

DateStage
31 July 2014Application submitted
30 October 2014Planning permission granted
1 January 2015Construction started
29 March 2015Operational

Project details

Technology
solar farm
Capacity
8.3 MW
Status (REPD)
operational
Record last updated
5 October 2015
Operator or applicant
KWTN Solar
Planning authority
North Somerset
Planning application reference
14/P/1666/F
Address (REPD)
Land at Bowerhouse East of Riverside Banwell
Council area (by location)
North Somerset
Time to decision
13 weeks
REPD reference
1518

Who decides

ApplicationsNorth SomersetUK
Decided applications (solar, wind, battery)4910,236
Refused7 (14%)19%
Solar refused2 of 3812%
Onshore wind refused0 of 145%
Battery storage refused5 of 1016%
Median time from submission to decision14.4 weeks17.0 weeks
Appeals lodged / allowed0 / 2—

Other large projects within 10 km

ProjectTypeMWStatuskm
Bowerhouse Farm (extension)solar farm19.8under construction0.9
Towerbrook Farm (Banwell Solar Farm)solar farm7.2operational1.6
Station Road & Nye Road, Sandfordbattery storage100application submitted2.2
Congresbury Solar Farmsolar farm7.1operational2.6
Yanel Farm, Churchill Green Solar Farmsolar farm49.9approved, not built2.6
Land at New Orchard Farmsolar farm5permission expired3.0
The Grangesolar farm8operational3.2
Manor Farm, Wick Lane Solar Farm & Battery Storagesolar farm49.9application submitted3.3
The Strawberry Line, Brinsea Road Solar Farmsolar farm49.9approved, not built4.2

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (51.345, -2.8611).