Energy Projects Near You

Land at New Orchard Farm (5 MW solar farm)

Land at New Orchard Farm is a 5 MW solar farm project in North Somerset, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: planning permission expired on 30 June 2018; the record was last updated on 25 April 2019.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

5 MWsolar farm
permission expiredstatus in REPD
25 April 2019record last updated
North Somersetcouncil area

Planning timeline

DateStage
20 October 2014Application submitted
30 June 2015Planning permission granted
30 June 2018Permission expired

Project details

Technology
solar farm
Capacity
5 MW
Status (REPD)
permission expired
Record last updated
25 April 2019
Operator or applicant
Solar Power South
Planning authority
North Somerset
Planning application reference
14/P/2283/F
Site area
10.2 ha
Address (REPD)
Land at New Orchard Farm, Puxton Lane, Hewish, Weston-Super-Mare
Council area (by location)
North Somerset
Time to decision
36 weeks
REPD reference
4741

Who decides

ApplicationsNorth SomersetUK
Decided applications (solar, wind, battery)4910,236
Refused7 (14%)19%
Solar refused2 of 3812%
Onshore wind refused0 of 145%
Battery storage refused5 of 1016%
Median time from submission to decision14.4 weeks17.0 weeks
Appeals lodged / allowed0 / 2—

Other large projects within 10 km

ProjectTypeMWStatuskm
The Grangesolar farm8operational1.7
Manor Farm, Wick Lane Solar Farm & Battery Storagesolar farm49.9application submitted1.9
Bowerhouse Farm (extension)solar farm19.8under construction2.1
Yew Tree Farm, Yew Tree Lane Solar Farmsolar farm50approved, not built2.7
Oldbridge, Congresbury Solar Farmsolar farm40application submitted2.9
Bowerhouse Farmsolar farm8.3operational3.0
Congresbury Solar Farmsolar farm7.1operational3.0
The Strawberry Line, Brinsea Road Solar Farmsolar farm49.9approved, not built3.2
Station Road & Nye Road, Sandfordbattery storage100application submitted4.2

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (51.3713, -2.8516).