Energy Projects Near You

Bowerhouse Farm (extension) (19.8 MW solar farm)

Bowerhouse Farm (extension) is a 19.8 MW solar farm project in North Somerset, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: under construction; the record was last updated on 4 November 2021.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

19.8 MWsolar farm
under constructionstatus in REPD
4 November 2021record last updated
North Somersetcouncil area

Planning timeline

DateStage
31 March 2020Application submitted
25 March 2022Planning permission granted

Project details

Technology
solar farm
Capacity
19.8 MW
Status (REPD)
under construction
Record last updated
4 November 2021
Operator or applicant
Ethical Power
Planning authority
North Somerset
Planning application reference
20/P/0620/FUL
Site area
40.0 ha
Address (REPD)
Photovoltaic Installation At B, Riverside, Banwell, Somerset
Council area (by location)
North Somerset
Time to decision
103 weeks
REPD reference
7539

Who decides

ApplicationsNorth SomersetUK
Decided applications (solar, wind, battery)4910,236
Refused7 (14%)19%
Solar refused2 of 3812%
Onshore wind refused0 of 145%
Battery storage refused5 of 1016%
Median time from submission to decision14.4 weeks17.0 weeks
Appeals lodged / allowed0 / 2—

Other large projects within 10 km

ProjectTypeMWStatuskm
Bowerhouse Farmsolar farm8.3operational0.9
Land at New Orchard Farmsolar farm5permission expired2.1
Towerbrook Farm (Banwell Solar Farm)solar farm7.2operational2.4
Congresbury Solar Farmsolar farm7.1operational2.4
The Grangesolar farm8operational2.4
Manor Farm, Wick Lane Solar Farm & Battery Storagesolar farm49.9application submitted2.6
Station Road & Nye Road, Sandfordbattery storage100application submitted2.6
Yanel Farm, Churchill Green Solar Farmsolar farm49.9approved, not built2.9
The Strawberry Line, Brinsea Road Solar Farmsolar farm49.9approved, not built3.7

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (51.3529, -2.859).