Energy Projects Near You

Towerbrook Farm (Banwell Solar Farm) (7.2 MW)

Towerbrook Farm (Banwell Solar Farm) is a 7.2 MW solar farm project in North Somerset, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: operational since 27 March 2015; the record was last updated on 1 December 2015.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

7.2 MWsolar farm
operationalstatus in REPD
1 December 2015record last updated
North Somersetcouncil area

Planning timeline

DateStage
26 August 2014Application submitted
28 November 2014Planning permission granted
1 December 2014Construction started
27 March 2015Operational

Project details

Technology
solar farm
Capacity
7.2 MW
Status (REPD)
operational
Record last updated
1 December 2015
Operator or applicant
Aquila Capital
Planning authority
North Somerset
Planning application reference
14/P/1842/F
Site area
14.8 ha
Address (REPD)
Land to north of Towerhead Road, Banwell
Council area (by location)
North Somerset
Time to decision
13 weeks
REPD reference
1203

Who decides

ApplicationsNorth SomersetUK
Decided applications (solar, wind, battery)4910,236
Refused7 (14%)19%
Solar refused2 of 3812%
Onshore wind refused0 of 145%
Battery storage refused5 of 1016%
Median time from submission to decision14.4 weeks17.0 weeks
Appeals lodged / allowed0 / 2—

Other large projects within 10 km

ProjectTypeMWStatuskm
Station Road & Nye Road, Sandfordbattery storage100application submitted1.5
Bowerhouse Farmsolar farm8.3operational1.6
Yanel Farm, Churchill Green Solar Farmsolar farm49.9approved, not built2.0
Bowerhouse Farm (extension)solar farm19.8under construction2.4
Congresbury Solar Farmsolar farm7.1operational2.9
Land at New Orchard Farmsolar farm5permission expired4.4
Brinsea Green Farm, Brinsea Lanesolar farm30approved, not built4.7
The Grangesolar farm8operational4.8
The Strawberry Line, Brinsea Road Solar Farmsolar farm49.9approved, not built4.8

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (51.3315, -2.8547).