Yanel Farm, Churchill Green Solar Farm (49.9 MW)

Yanel Farm, Churchill Green Solar Farm is a 49.9 MW solar farm project in North Somerset, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: approved on 18 April 2024, not yet built; the record was last updated on 8 April 2026.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

49.9 MWsolar farm
approved, not builtstatus in REPD
8 April 2026record last updated
North Somersetcouncil area

Planning timeline

DateStage
15 July 2022Application submitted
18 April 2024Planning permission granted
18 April 2027Permission due to expire (unless work starts)

Project details

Technology
solar farm
Capacity
49.9 MW
Status (REPD)
approved, not built
Record last updated
8 April 2026
Operator or applicant
Capital Dynamics Limited
Planning authority
North Somerset
Planning application reference
22/P/1450/FUL
Site area
67.2 ha
Address (REPD)
Yanel Farm Churchill Green Churchill
Council area (by location)
North Somerset
Time to decision
92 weeks
Contracts for Difference
AR6
Name in REPD
Yanel Farm, Churchill Green - Solar Farm
REPD reference
11783

Who decides

ApplicationsNorth SomersetUK
Decided applications (solar, wind, battery)4910,236
Refused7 (14%)19%
Solar refused2 of 3812%
Onshore wind refused0 of 145%
Battery storage refused5 of 1016%
Median time from submission to decision14.4 weeks17.0 weeks
Appeals lodged / allowed0 / 2—

Other large projects within 10 km

ProjectTypeMWStatuskm
Station Road & Nye Road, Sandfordbattery storage100application submitted0.5
Congresbury Solar Farmsolar farm7.1operational1.6
Towerbrook Farm (Banwell Solar Farm)solar farm7.2operational2.0
Bowerhouse Farmsolar farm8.3operational2.6
Brinsea Green Farm, Brinsea Lanesolar farm30approved, not built2.9
Bowerhouse Farm (extension)solar farm19.8under construction2.9
The Strawberry Line, Brinsea Road Solar Farmsolar farm49.9approved, not built3.3
Iwood Lane Solar Farmsolar farm8operational3.6
Yeowood Farmbattery storage49.9refused3.8

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (51.336, -2.8266).