Solar, wind and battery projects near Banwell (BS29)
48 solar, wind or battery projects of 150 kW or more are recorded within 10 km of the centre of BS29 (North Somerset): 6 are waiting for a planning decision, 27 approved but not yet running, 9 operational. The largest live scheme is Station Road & Nye Road, Sandford (100 MW battery storage, application submitted on 12 June 2025, no decision recorded), 3.2 km away. Source: Renewable Energy Planning Database, July 2026 extract.
Projects within 10 km of BS29
Projects of 1 MW and more (28)
| Project | Type | MW | Status (REPD) | Submitted | Decision | Record updated | Council | km |
|---|---|---|---|---|---|---|---|---|
| Towerbrook Farm (Banwell Solar Farm)solar farm | solar farm | 7.2 | operationalupdated Dec 2015 | Aug 2014 | granted Nov 2014 | Dec 2015 | North Somerset | 1.8 |
| Bowerhouse Farmsolar farm | solar farm | 8.3 | operationalupdated Oct 2015 | Jul 2014 | granted Oct 2014 | Oct 2015 | North Somerset | 1.9 |
| Bowerhouse Farm (extension)solar farm | solar farm | 19.8 | under constructionupdated Nov 2021 | Mar 2020 | granted Mar 2022 | Nov 2021 | North Somerset | 2.6 |
| Station Road & Nye Road, Sandfordbattery storage | battery storage | 100 | application submittedupdated Aug 2025 | Jun 2025 | — | Aug 2025 | North Somerset | 3.2 |
| Yanel Farm, Churchill Green Solar Farmsolar farm | solar farm | 49.9 | approved, not builtupdated Apr 2026 | Jul 2022 | granted Apr 2024 | Apr 2026 | North Somerset | 3.7 |
| Congresbury Solar Farmsolar farm | solar farm | 7.1 | operationalupdated Mar 2016 | Jun 2014 | granted Nov 2014 | Mar 2016 | North Somerset | 4.3 |
| The Grangesolar farm | solar farm | 8 | operationalupdated Jan 2017 | Sep 2014 | granted Feb 2015 | Jan 2017 | North Somerset | 4.3 |
| Manor Farm, Wick Lane Solar Farm & Battery Storagesolar farm | solar farm | 49.9 | application submittedupdated Feb 2026 | Jan 2026 | — | Feb 2026 | North Somerset | 4.4 |
| Manor Farm, Wick Lane Solar Farm & Battery Storagebattery storage | battery storage | 24 | application submittedupdated Feb 2026 | Jan 2026 | — | Feb 2026 | North Somerset | 4.4 |
| Land at New Orchard Farmsolar farm | solar farm | 5 | permission expiredupdated Apr 2019 | Oct 2014 | granted Jun 2015 | Apr 2019 | North Somerset | 4.7 |
| The Strawberry Line, Brinsea Road Solar Farmsolar farm | solar farm | 49.9 | approved, not builtupdated Feb 2026 | Apr 2025 | granted Aug 2025 | Feb 2026 | North Somerset | 6.0 |
| South Hill Farm solar parksolar farm | solar farm | 7.8 | refusedupdated Sep 2013 | May 2013 | refused Aug 2013 | Sep 2013 | North Somerset | 6.2 |
| Townsend Farmsolar farm | solar farm | 4.9 | refused on appealupdated Mar 2017 | Sep 2015 | refused Dec 2015 | Mar 2017 | Somerset | 6.2 |
| Brinsea Green Farm, Brinsea Lanesolar farm | solar farm | 30 | approved, not builtupdated Feb 2026 | Oct 2023 | granted Feb 2025 | Feb 2026 | North Somerset | 6.2 |
| Oldbridge, Congresbury Solar Farmsolar farm | solar farm | 40 | application submittedupdated Jun 2026 | Jun 2025 | — | Jun 2026 | North Somerset | 6.4 |
| Twin Elm Solar Farmsolar farm | solar farm | 1 | operationalupdated Dec 2013 | Mar 2012 | granted Jun 2012 | Dec 2013 | North Somerset | 6.5 |
| Sandbay, Elmsley Lane, Kewstoke Solar Farmsolar farm | solar farm | 24.5 | approved, not builtupdated Feb 2026 | Feb 2023 | granted Oct 2024 | Feb 2026 | North Somerset | 6.5 |
| Iwood Lane Solar Farmsolar farm | solar farm | 8 | operationalupdated Jun 2015 | Dec 2013 | granted May 2014 | Jun 2015 | North Somerset | 6.8 |
| Yew Tree Farm, Yew Tree Lane Solar Farmsolar farm | solar farm | 50 | approved, not builtupdated Nov 2025 | Jul 2025 | granted Oct 2025 | Nov 2025 | North Somerset | 6.8 |
| Yeowood Farmbattery storage | battery storage | 49.9 | refusedupdated Jan 2025 | Aug 2024 | refused Dec 2024 | Jan 2025 | North Somerset | 7.1 |
| Smart Systems Limited, Arnolds Wayrooftop solar | rooftop solar | 2.9 | under constructionupdated Nov 2023 | Jul 2023 | granted Oct 2023 | Nov 2023 | North Somerset | 7.2 |
| Smart Systemsrooftop solar | rooftop solar | 1 | approved, not built may be out of dateupdated Jun 2019 | Apr 2015 | granted Sep 2015 | Jun 2019 | North Somerset | 7.2 |
| Smart Systemswind farm | wind farm | 1 | approved, not built may be out of dateupdated Mar 2020 | Apr 2015 | granted Sep 2015 | Mar 2020 | North Somerset | 7.2 |
| Kitland Solar Farmsolar farm | solar farm | 40 | approved, not builtupdated Feb 2026 | May 2024 | granted Dec 2024 | Feb 2026 | North Somerset | 7.8 |
| Wick Farm Solar Parksolar farm | solar farm | 14.6 | operationalupdated Jan 2016 | Aug 2014 | granted Oct 2014 | Jan 2016 | Somerset | 8.7 |
| Pilrowwind farm | wind farm | 12 | refused on appealupdated Sep 2014 | Jun 2012 | refused Apr 2013 | Sep 2014 | Somerset | 8.7 |
| Ashlawn Farmsolar farm | solar farm | 6.8 | operationalupdated Feb 2015 | Mar 2014 | granted May 2014 | Feb 2015 | Somerset | 8.8 |
| Wick Lane Solar Ltdsolar farm | solar farm | 2.8 | operationalupdated Apr 2017 | Jul 2015 | granted Dec 2015 | Apr 2017 | Somerset | 9.1 |
Smaller schemes under 1 MW, mostly rooftop solar (20)
| Project | Type | MW | Status (REPD) | Submitted | Decision | Record updated | Council | km |
|---|---|---|---|---|---|---|---|---|
| Morrisons, Worle Moor Gaterooftop solar | rooftop solar | 0.3 | approved, not builtupdated Apr 2024 | Jan 2024 | granted Mar 2024 | Apr 2024 | North Somerset | 3.2 |
| Bransby Way, Heron Moor School - Micro Energy Storage Facilitybattery storage | battery storage | 0.2 | application submittedupdated May 2026 | Apr 2026 | — | May 2026 | North Somerset | 3.4 |
| Weston Youth Centre, Coleridge Roadbattery storage | battery storage | 0.2 | approved, not builtupdated Apr 2026 | Mar 2025 | granted Feb 2026 | Apr 2026 | North Somerset | 5.7 |
| Bournville Primary School, Selworthy Roadrooftop solar | rooftop solar | 0.3 | approved, not builtupdated Jan 2026 | Sep 2025 | granted Dec 2025 | Jan 2026 | North Somerset | 5.9 |
| Weston Fire Station, Summerlands Road - Micro Energy Storagebattery storage | battery storage | 0.2 | refusedupdated Jun 2025 | Apr 2025 | refused Jun 2025 | Jun 2025 | North Somerset | 5.9 |
| The Strawberry Line, Brinsea Roadbattery storage | battery storage | — | approved, not builtupdated Feb 2026 | Apr 2025 | granted Aug 2025 | Feb 2026 | North Somerset | 6.0 |
| Westbury Crescent, Loxton Road - Micro Energy Storage Facilitybattery storage | battery storage | 0.2 | approved, not builtupdated Apr 2026 | Mar 2025 | granted Feb 2026 | Apr 2026 | North Somerset | 6.1 |
| Sewage Treatment Works, Warth Lanesolar farm | solar farm | — | approved, not builtupdated Nov 2023 | Oct 2023 | granted Nov 2023 | Nov 2023 | North Somerset | 6.1 |
| Brinsea Green Farm, Brinsea Lanebattery storage | battery storage | — | approved, not builtupdated Feb 2026 | Oct 2023 | granted Feb 2025 | Feb 2026 | North Somerset | 6.2 |
| Weston College University Campus, Loxton Road - Air Source Heat Pumpsrooftop solar | rooftop solar | 0.4 | approved, not builtupdated May 2025 | Feb 2025 | granted Apr 2025 | May 2025 | North Somerset | 6.3 |
| Weston Collegerooftop solar | rooftop solar | 0.3 | approved, not builtupdated Apr 2025 | Jan 2025 | granted Apr 2025 | Apr 2025 | North Somerset | 6.3 |
| Weston General Hospital - Photovoltaic Installation Projectrooftop solar | rooftop solar | — | application submitted may be out of dateupdated Aug 2021 | Aug 2021 | — | Aug 2021 | North Somerset | 6.5 |
| Langford - Roof Mounted Solar Photovoltaic Panelsrooftop solar | rooftop solar | 0.6 | approved, not builtupdated Mar 2022 | Mar 2022 | granted Apr 2022 | Mar 2022 | North Somerset | 6.7 |
| Cadbury Garden And Leisurerooftop solar | rooftop solar | 0.5 | approved, not builtupdated Dec 2021 | Oct 2021 | granted Nov 2021 | Dec 2021 | North Somerset | 6.8 |
| Callow Rock Quarry, Shipham Roadrooftop solar | rooftop solar | 0.2 | approved, not builtupdated Dec 2024 | Sep 2024 | granted Nov 2024 | Dec 2024 | Somerset | 7.0 |
| Arnolds Way, Yattonrooftop solar | rooftop solar | 0.8 | under constructionupdated Mar 2022 | Feb 2022 | granted Oct 2022 | Mar 2022 | North Somerset | 7.1 |
| Lower Stock Farm, Langfordbattery storage | battery storage | — | approved, not builtupdated Feb 2026 | May 2024 | granted Dec 2024 | Feb 2026 | North Somerset | 7.8 |
| Bellcombe Works, Brent Roadrooftop solar | rooftop solar | 0.6 | approved, not built may be out of dateupdated Sep 2022 | Aug 2022 | granted Sep 2022 | Sep 2022 | Somerset | 8.7 |
| Cheddar Water Recycling Centre, Wedmore Road Solar Farmsolar farm | solar farm | — | approved, not builtupdated Dec 2023 | Oct 2023 | granted Nov 2023 | Dec 2023 | Somerset | 9.4 |
| Lower Strode Roadrooftop solar | rooftop solar | 0.3 | approved, not builtupdated Jul 2022 | Jul 2022 | granted Aug 2022 | Jul 2022 | North Somerset | 9.7 |
Distance from the average position of the BS29 postcodes, not from your home. Projects of 5 MW and more have their own page with dates and planning history.
By type
| Type | All | Pending | Approved | Operational | Refused | MW in pipeline |
|---|---|---|---|---|---|---|
| Solar farm | 23 | 2 | 9 | 9 | 2 | 354 |
| Rooftop solar | 13 | 1 | 12 | 0 | 0 | 8.4 |
| Wind farm | 2 | 0 | 1 | 0 | 1 | 1 |
| Battery storage | 10 | 3 | 5 | 0 | 2 | 125 |
MW in pipeline: pending, approved and under-construction capacity.
How North Somerset decides solar, wind and battery applications
| Applications | North Somerset | UK |
|---|---|---|
| Decided applications (solar, wind, battery) | 49 | 10,236 |
| Refused | 7 (14%) | 19% |
| Solar refused | 2 of 38 | 12% |
| Onshore wind refused | 0 of 1 | 45% |
| Battery storage refused | 5 of 10 | 16% |
| Median time from submission to decision | 14.4 weeks | 17.0 weeks |
| Appeals lodged / allowed | 0 / 2 | — |
All projects in North Somerset
Is the status up to date?
32% of applications still shown as pending in REPD were submitted more than two years ago, and only 37% of pending records were updated in the last 12 months, so some of them may already have been decided. Near BS29, 4 projects have a status that may be out of date (pending for over two years, or approved with a permission expiry date already passed). Check the council's planning register for the latest decision.