Wick Farm Solar Park (14.6 MW)

Wick Farm Solar Park is a 14.6 MW solar farm project in Somerset, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: operational since 1 July 2016; the record was last updated on 4 January 2016.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

14.6 MWsolar farm
operationalstatus in REPD
4 January 2016record last updated
Somersetcouncil area

Planning timeline

DateStage
20 August 2014Application submitted
28 October 2014Planning permission granted
1 April 2016Construction started
1 July 2016Operational

Project details

Technology
solar farm
Capacity
14.6 MW
Status (REPD)
operational
Record last updated
4 January 2016
Operator or applicant
Hadstone Energy/ Communities for Renewables
Planning authority
Somerset
Planning application reference
05/14/00019
Site area
36.6 ha
Address (REPD)
S/O Wick Farm, Brean Road, Lympsham, Weston Super Mare, North Somerset
Council area (by location)
Somerset
Time to decision
10 weeks
REPD reference
2274

Who decides

ApplicationsSomersetUK
Decided applications (solar, wind, battery)18510,236
Refused46 (25%)19%
Solar refused34 of 15312%
Onshore wind refused9 of 1045%
Battery storage refused3 of 2216%
Median time from submission to decision14.0 weeks17.0 weeks
Appeals lodged / allowed17 / 9—

Other large projects within 10 km

ProjectTypeMWStatuskm
South Hill Farm solar parksolar farm7.8refused2.8
Inner Farmwind farm10refused4.6
Pilrowwind farm12refused on appeal5.6
Ashlawn Farmsolar farm6.8operational6.4
Watchfield Lawnsolar farm10.2operational7.3
Sandbay, Elmsley Lane, Kewstoke Solar Farmsolar farm24.5approved, not built9.9

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (51.2871, -2.9813).