Inner Farm (10 MW wind farm)
Inner Farm is a 10 MW wind farm project in Somerset, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: refused on 8 August 2006; the record was last updated on 6 July 2009.
10 MWwind farm
refusedstatus in REPD
6 July 2009record last updated
Somersetcouncil area
Planning timeline
| Date | Stage |
|---|---|
| 22 March 2006 | Application submitted |
| 8 August 2006 | Refused by the planning authority |
Project details
- Technology
- wind farm
- Capacity
- 10 MW
- Status (REPD)
- refused
- Record last updated
- 6 July 2009
- Operator or applicant
- Ecotricity
- Planning authority
- Somerset
- Planning application reference
- 12/06/00007
- Turbines
- 5
- Address (REPD)
- Inner Farm, Stoddens Lane, Edithmead, Highbridge, Sedgemoor
- Council area (by location)
- Somerset
- Time to decision
- 20 weeks
- REPD reference
- 2919
Who decides
| Applications | Somerset | UK |
|---|---|---|
| Decided applications (solar, wind, battery) | 185 | 10,236 |
| Refused | 46 (25%) | 19% |
| Solar refused | 34 of 153 | 12% |
| Onshore wind refused | 9 of 10 | 45% |
| Battery storage refused | 3 of 22 | 16% |
| Median time from submission to decision | 14.0 weeks | 17.0 weeks |
| Appeals lodged / allowed | 17 / 9 | — |
Other large projects within 10 km
| Project | Type | MW | Status | km |
|---|---|---|---|---|
| Watchfield Lawn | solar farm | 10.2 | operational | 2.8 |
| Pilrow | wind farm | 12 | refused on appeal | 3.8 |
| Ashlawn Farm | solar farm | 6.8 | operational | 4.5 |
| Wick Farm Solar Park | solar farm | 14.6 | operational | 4.6 |
| Huntspill Level Solar Park | solar farm | 5.5 | operational | 5.8 |
| Black Ditch | wind farm | 9.2 | refused | 5.9 |
| Withy End | wind farm | 10 | refused | 6.8 |
| South Hill Farm solar park | solar farm | 7.8 | refused | 6.9 |
| Puriton Landfill Solar Farm | solar farm | 11.4 | operational | 7.6 |
Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (51.2465, -2.967).