Energy Projects Near You

Inner Farm (10 MW wind farm)

Inner Farm is a 10 MW wind farm project in Somerset, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: refused on 8 August 2006; the record was last updated on 6 July 2009.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

10 MWwind farm
refusedstatus in REPD
6 July 2009record last updated
Somersetcouncil area

Planning timeline

DateStage
22 March 2006Application submitted
8 August 2006Refused by the planning authority

Project details

Technology
wind farm
Capacity
10 MW
Status (REPD)
refused
Record last updated
6 July 2009
Operator or applicant
Ecotricity
Planning authority
Somerset
Planning application reference
12/06/00007
Turbines
5
Address (REPD)
Inner Farm, Stoddens Lane, Edithmead, Highbridge, Sedgemoor
Council area (by location)
Somerset
Time to decision
20 weeks
REPD reference
2919

Who decides

ApplicationsSomersetUK
Decided applications (solar, wind, battery)18510,236
Refused46 (25%)19%
Solar refused34 of 15312%
Onshore wind refused9 of 1045%
Battery storage refused3 of 2216%
Median time from submission to decision14.0 weeks17.0 weeks
Appeals lodged / allowed17 / 9—

Other large projects within 10 km

ProjectTypeMWStatuskm
Watchfield Lawnsolar farm10.2operational2.8
Pilrowwind farm12refused on appeal3.8
Ashlawn Farmsolar farm6.8operational4.5
Wick Farm Solar Parksolar farm14.6operational4.6
Huntspill Level Solar Parksolar farm5.5operational5.8
Black Ditchwind farm9.2refused5.9
Withy Endwind farm10refused6.8
South Hill Farm solar parksolar farm7.8refused6.9
Puriton Landfill Solar Farmsolar farm11.4operational7.6

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (51.2465, -2.967).