Energy Projects Near You

Solar, wind and battery projects near Highbridge (TA9)

22 solar, wind or battery projects of 150 kW or more are recorded within 10 km of the centre of TA9 (Somerset): 2 are waiting for a planning decision, 3 approved but not yet running, 11 operational. The largest live scheme is Saltlands Avenue Solar Parks (8.9 MW solar farm, application submitted on 11 January 2022, no decision recorded; REPD status may be out of date), 9.5 km away. Source: Renewable Energy Planning Database, July 2026 extract.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

22projects within 10 km
2awaiting a decision
3approved, not running
11operational

Projects within 10 km of TA9

Projects of 1 MW and more (18)

ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updatedCouncilkm
Watchfield Lawnsolar farmsolar farm10.2operationalupdated Dec 2014May 2013granted Aug 2013Dec 2014Somerset0.9
Inner Farmwind farmwind farm10refusedupdated Jul 2009Mar 2006refused Aug 2006Jul 2009Somerset2.5
Yardwall Manorsolar farmsolar farm3operationalupdated May 2018Jul 2014granted Sep 2014May 2018Somerset3.2
Huntspill Level Solar Parksolar farmsolar farm5.5operationalupdated Jan 2017Jun 2015granted Sep 2015Jan 2017Somerset3.5
Black Ditchwind farmwind farm9.2refusedupdated May 2015Dec 2010refused Apr 2012May 2015Somerset3.9
Withy Endwind farmwind farm10refusedupdated May 2015Dec 2013refused May 2015May 2015Somerset4.4
Pilrowwind farmwind farm12refused on appealupdated Sep 2014Jun 2012refused Apr 2013Sep 2014Somerset4.6
Wick Lane Solar Ltdsolar farmsolar farm2.8operationalupdated Apr 2017Jul 2015granted Dec 2015Apr 2017Somerset5.0
Ashlawn Farmsolar farmsolar farm6.8operationalupdated Feb 2015Mar 2014granted May 2014Feb 2015Somerset5.0
Puriton Landfill Solar Farmsolar farmsolar farm11.4operationalupdated Feb 2016Jun 2014granted Sep 2014Feb 2016Somerset5.4
Puriton Solar Farmsolar farmsolar farm4.6operationalupdated Oct 2012Feb 2011granted May 2011Oct 2012Somerset5.6
Pyde Drovesolar farmsolar farm7operationalupdated Aug 2014Aug 2013granted Oct 2013Aug 2014Somerset5.7
Land to the South West of Horsey Lanesolar farmsolar farm25refused on appealupdated Jan 2016Jan 2015refused Apr 2015Jan 2016Somerset6.2
Wick Farm Solar Parksolar farmsolar farm14.6operationalupdated Jan 2016Aug 2014granted Oct 2014Jan 2016Somerset7.1
Horsey Levels Solar Farmsolar farmsolar farm24operationalupdated Mar 2024Dec 2021granted Mar 2022Mar 2024Somerset7.2
South Hill Farm solar parksolar farmsolar farm7.8refusedupdated Sep 2013May 2013refused Aug 2013Sep 2013North Somerset9.3
Land at Mill Farmsolar farmsolar farm1operationalupdated Feb 2014Jan 2013granted Apr 2013Feb 2014Somerset9.4
Saltlands Avenue Solar Parkssolar farmsolar farm8.9application submitted may be out of dateupdated Dec 2023Jan 2022—Dec 2023Somerset9.5
Smaller schemes under 1 MW, mostly rooftop solar (4)
ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updatedCouncilkm
Burnham Holiday Village, Marine Drive Solar Photovoltaicsrooftop solarrooftop solar0.1approved, not builtupdated Feb 2023Dec 2022granted Jan 2023Feb 2023Somerset2.8
Bellcombe Works, Brent Roadrooftop solarrooftop solar0.6approved, not built may be out of dateupdated Sep 2022Aug 2022granted Sep 2022Sep 2022Somerset4.6
Butcombe Beer Store, The Polden Business Centrerooftop solarrooftop solar0.3approved, not builtupdated Mar 2023Dec 2022granted Mar 2023Mar 2023Somerset8.4
Saltlands Avenue -Battery Storagebattery storagebattery storage—application submitted may be out of dateupdated Dec 2023Jan 2022—Dec 2023Somerset9.5

Distance from the average position of the TA9 postcodes, not from your home. Projects of 5 MW and more have their own page with dates and planning history.

By type

TypeAllPendingApprovedOperationalRefusedMW in pipeline
Solar farm14101128.9
Rooftop solar303001
Wind farm400040
Battery storage110000

MW in pipeline: pending, approved and under-construction capacity.

How Somerset decides solar, wind and battery applications

ApplicationsSomersetUK
Decided applications (solar, wind, battery)18510,236
Refused46 (25%)19%
Solar refused34 of 15312%
Onshore wind refused9 of 1045%
Battery storage refused3 of 2216%
Median time from submission to decision14.0 weeks17.0 weeks
Appeals lodged / allowed17 / 9—

All projects in Somerset

Is the status up to date?

32% of applications still shown as pending in REPD were submitted more than two years ago, and only 37% of pending records were updated in the last 12 months, so some of them may already have been decided. Near TA9, 3 projects have a status that may be out of date (pending for over two years, or approved with a permission expiry date already passed). Check the council's planning register for the latest decision.