Pyde Drove (7 MW solar farm)

Pyde Drove is a 7 MW solar farm project in Somerset, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: operational since 27 March 2014; the record was last updated on 26 August 2014.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

7 MWsolar farm
operationalstatus in REPD
26 August 2014record last updated
Somersetcouncil area

Planning timeline

DateStage
9 August 2013Application submitted
31 October 2013Planning permission granted
27 March 2014Operational

Project details

Technology
solar farm
Capacity
7 MW
Status (REPD)
operational
Record last updated
26 August 2014
Operator or applicant
Wessex Solar Energy
Planning authority
Somerset
Planning application reference
54/13/00010
Site area
18.7 ha
Address (REPD)
Land at, Pyde Drove (2), The Causeway, Woolavington, Bridgwater
Council area (by location)
Somerset
Time to decision
12 weeks
REPD reference
2015

Who decides

ApplicationsSomersetUK
Decided applications (solar, wind, battery)18510,236
Refused46 (25%)19%
Solar refused34 of 15312%
Onshore wind refused9 of 1045%
Battery storage refused3 of 2216%
Median time from submission to decision14.0 weeks17.0 weeks
Appeals lodged / allowed17 / 9—

Other large projects within 10 km

ProjectTypeMWStatuskm
Land to the South West of Horsey Lanesolar farm25refused on appeal2.1
Withy Endwind farm10refused2.3
Huntspill Level Solar Parksolar farm5.5operational3.2
Puriton Landfill Solar Farmsolar farm11.4operational3.8
Horsey Levels Solar Farmsolar farm24operational4.2
Black Ditchwind farm9.2refused4.9
Watchfield Lawnsolar farm10.2operational5.5
Saltlands Avenue Solar Parkssolar farm8.9application submitted6.3
Summerway Drove, East Bowerbattery storage90approved, not built6.3

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (51.1781, -2.9237).