Watchfield Lawn (10.2 MW solar farm)

Watchfield Lawn is a 10.2 MW solar farm project in Somerset, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: operational since 12 March 2014; the record was last updated on 1 December 2014.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

10.2 MWsolar farm
operationalstatus in REPD
1 December 2014record last updated
Somersetcouncil area

Planning timeline

DateStage
24 May 2013Application submitted
1 August 2013Planning permission granted
7 November 2013Construction started
12 March 2014Operational

Project details

Technology
solar farm
Capacity
10.2 MW
Status (REPD)
operational
Record last updated
1 December 2014
Operator or applicant
Belltown Power
Planning authority
Somerset
Planning application reference
12/13/00009
Site area
26.6 ha
Address (REPD)
Land at, Watchfield Lawn, Watchfield, Highbridge, TA9 4LD
Council area (by location)
Somerset
Time to decision
10 weeks
REPD reference
1681

Who decides

ApplicationsSomersetUK
Decided applications (solar, wind, battery)18510,236
Refused46 (25%)19%
Solar refused34 of 15312%
Onshore wind refused9 of 1045%
Battery storage refused3 of 2216%
Median time from submission to decision14.0 weeks17.0 weeks
Appeals lodged / allowed17 / 9—

Other large projects within 10 km

ProjectTypeMWStatuskm
Inner Farmwind farm10refused2.8
Huntspill Level Solar Parksolar farm5.5operational3.7
Pilrowwind farm12refused on appeal4.1
Ashlawn Farmsolar farm6.8operational4.4
Withy Endwind farm10refused4.4
Black Ditchwind farm9.2refused4.5
Pyde Drovesolar farm7operational5.5
Puriton Landfill Solar Farmsolar farm11.4operational5.7
Land to the South West of Horsey Lanesolar farm25refused on appeal6.2

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (51.2253, -2.9446).