Energy Projects Near You

Huntspill Level Solar Park (5.5 MW)

Huntspill Level Solar Park is a 5.5 MW solar farm project in Somerset, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: operational since 15 March 2016; the record was last updated on 25 January 2017.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

5.5 MWsolar farm
operationalstatus in REPD
25 January 2017record last updated
Somersetcouncil area

Planning timeline

DateStage
19 June 2015Application submitted
11 September 2015Planning permission granted
15 January 2016Construction started
15 March 2016Operational

Project details

Technology
solar farm
Capacity
5.5 MW
Status (REPD)
operational
Record last updated
25 January 2017
Operator or applicant
Wessex Solar Energy
Planning authority
Somerset
Planning application reference
25/15/00014
Site area
15.5 ha
Address (REPD)
Bangor (bounded by Belfast Road
Council area (by location)
Somerset
Time to decision
12 weeks
REPD reference
5440

Who decides

ApplicationsSomersetUK
Decided applications (solar, wind, battery)18510,236
Refused46 (25%)19%
Solar refused34 of 15312%
Onshore wind refused9 of 1045%
Battery storage refused3 of 2216%
Median time from submission to decision14.0 weeks17.0 weeks
Appeals lodged / allowed17 / 9—

Other large projects within 10 km

ProjectTypeMWStatuskm
Withy Endwind farm10refused1.1
Black Ditchwind farm9.2refused1.8
Puriton Landfill Solar Farmsolar farm11.4operational2.1
Land to the South West of Horsey Lanesolar farm25refused on appeal2.9
Pyde Drovesolar farm7operational3.2
Watchfield Lawnsolar farm10.2operational3.7
Horsey Levels Solar Farmsolar farm24operational3.8
Inner Farmwind farm10refused5.8
Saltlands Avenue Solar Parkssolar farm8.9application submitted6.2

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (51.1943, -2.962).