Black Ditch (9.2 MW wind farm)

Black Ditch is a 9.2 MW wind farm project in Somerset, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: refused on 24 April 2012; the record was last updated on 20 May 2015.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

9.2 MWwind farm
refusedstatus in REPD
20 May 2015record last updated
Somersetcouncil area

Planning timeline

DateStage
1 December 2010Application submitted
24 April 2012Refused by the planning authority
29 October 2012Appeal lodged
11 October 2013Secretary of State intervened
25 February 2014Secretary of State refused
26 February 2014Appeal refused

Project details

Technology
wind farm
Capacity
9.2 MW
Status (REPD)
refused
Record last updated
20 May 2015
Operator or applicant
Ecotricity
Planning authority
Somerset
Planning application reference
52/10/00018
Turbines
4
Address (REPD)
Pawlett Road, Near West Huntspill, Somerset
Council area (by location)
Somerset
Time to decision
73 weeks
REPD reference
4148

Who decides

ApplicationsSomersetUK
Decided applications (solar, wind, battery)18510,236
Refused46 (25%)19%
Solar refused34 of 15312%
Onshore wind refused9 of 1045%
Battery storage refused3 of 2216%
Median time from submission to decision14.0 weeks17.0 weeks
Appeals lodged / allowed17 / 9—

Other large projects within 10 km

ProjectTypeMWStatuskm
Huntspill Level Solar Parksolar farm5.5operational1.8
Puriton Landfill Solar Farmsolar farm11.4operational2.0
Withy Endwind farm10refused2.6
Horsey Levels Solar Farmsolar farm24operational3.8
Land to the South West of Horsey Lanesolar farm25refused on appeal3.9
Watchfield Lawnsolar farm10.2operational4.5
Pyde Drovesolar farm7operational4.9
Saltlands Avenue Solar Parkssolar farm8.9application submitted5.9
Inner Farmwind farm10refused5.9

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (51.1954, -2.9877).