Energy Projects Near You

Saltlands Avenue Solar Parks (8.9 MW)

Saltlands Avenue Solar Parks is an 8.9 MW solar farm project in Somerset, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: application submitted on 11 January 2022, no decision recorded; the record was last updated on 14 December 2023. The application was submitted more than two years ago and is still shown as pending; it may have been decided since. Check the planning authority's register for the latest position.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

8.9 MWsolar farm
application submittedmay be out of datestatus in REPD
14 December 2023record last updated
Somersetcouncil area

The application was submitted more than two years ago and is still shown as pending; it may have been decided since. 32% of applications still shown as pending in REPD were submitted more than two years ago, and only 37% of pending records were updated in the last 12 months, so some of them may already have been decided.

Planning timeline

DateStage
11 January 2022Application submitted

Project details

Technology
solar farm
Capacity
8.9 MW
Status (REPD)
application submitted
Record last updated
14 December 2023
Operator or applicant
Somerset County Council
Planning authority
Somerset
Planning application reference
20/22/00001
Site area
12.1 ha
Address (REPD)
Saltlands Avenue, Bridgwater
Council area (by location)
Somerset
Name in REPD
Saltlands Avenue - Solar Parks
REPD reference
10135

Recorded together with Saltlands Avenue -Battery Storage (battery storage, application submitted).

Who decides

ApplicationsSomersetUK
Decided applications (solar, wind, battery)18510,236
Refused46 (25%)19%
Solar refused34 of 15312%
Onshore wind refused9 of 1045%
Battery storage refused3 of 2216%
Median time from submission to decision14.0 weeks17.0 weeks
Appeals lodged / allowed17 / 9—

Other large projects within 10 km

ProjectTypeMWStatuskm
Horsey Levels Solar Farmsolar farm24operational2.4
Summerway Drove, East Bowerbattery storage90approved, not built2.6
Park Wall Solar Parksolar farm5operational3.1
Puriton Landfill Solar Farmsolar farm11.4operational4.1
Land to the South West of Horsey Lanesolar farm25refused on appeal4.3
Cobbs Cross Solar Parksolar farm5operational4.5
Withy Endwind farm10refused5.6
Black Ditchwind farm9.2refused5.9
Huntspill Level Solar Parksolar farm5.5operational6.2

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (51.143, -2.9948).