Energy Projects Near You

Solar, wind and battery projects near Wedmore (BS28)

11 solar, wind or battery projects of 150 kW or more are recorded within 10 km of the centre of BS28 (Somerset): 3 approved but not yet running, 6 operational. The largest live scheme is Bellcombe Works, Brent Road (0.6 MW rooftop solar, approved on 15 September 2022, not yet built; REPD status may be out of date), 9.8 km away. Source: Renewable Energy Planning Database, July 2026 extract.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

11projects within 10 km
0awaiting a decision
3approved, not running
6operational

Projects within 10 km of BS28

Projects of 1 MW and more (8)

ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updatedCouncilkm
Land at Mill Farmsolar farmsolar farm1operationalupdated Feb 2014Jan 2013granted Apr 2013Feb 2014Somerset0.6
Hawkers Farmsolar farmsolar farm9.5operationalupdated Apr 2015Nov 2014granted Feb 2015Apr 2015Somerset3.6
Yardwall Manorsolar farmsolar farm3operationalupdated May 2018Jul 2014granted Sep 2014May 2018Somerset6.7
Townsend Farmsolar farmsolar farm4.9refused on appealupdated Mar 2017Sep 2015refused Dec 2015Mar 2017Somerset7.0
Ashlawn Farmsolar farmsolar farm6.8operationalupdated Feb 2015Mar 2014granted May 2014Feb 2015Somerset7.0
Pilrowwind farmwind farm12refused on appealupdated Sep 2014Jun 2012refused Apr 2013Sep 2014Somerset7.8
Watchfield Lawnsolar farmsolar farm10.2operationalupdated Dec 2014May 2013granted Aug 2013Dec 2014Somerset9.0
Pyde Drovesolar farmsolar farm7operationalupdated Aug 2014Aug 2013granted Oct 2013Aug 2014Somerset9.3
Smaller schemes under 1 MW, mostly rooftop solar (3)
ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updatedCouncilkm
Cheddar Water Recycling Centre, Wedmore Road Solar Farmsolar farmsolar farm—approved, not builtupdated Dec 2023Oct 2023granted Nov 2023Dec 2023Somerset4.8
Callow Rock Quarry, Shipham Roadrooftop solarrooftop solar0.2approved, not builtupdated Dec 2024Sep 2024granted Nov 2024Dec 2024Somerset8.4
Bellcombe Works, Brent Roadrooftop solarrooftop solar0.6approved, not built may be out of dateupdated Sep 2022Aug 2022granted Sep 2022Sep 2022Somerset9.8

Distance from the average position of the BS28 postcodes, not from your home. Projects of 5 MW and more have their own page with dates and planning history.

By type

TypeAllPendingApprovedOperationalRefusedMW in pipeline
Solar farm801610
Rooftop solar202000.8
Wind farm100010

MW in pipeline: pending, approved and under-construction capacity.

How Somerset decides solar, wind and battery applications

ApplicationsSomersetUK
Decided applications (solar, wind, battery)18510,236
Refused46 (25%)19%
Solar refused34 of 15312%
Onshore wind refused9 of 1045%
Battery storage refused3 of 2216%
Median time from submission to decision14.0 weeks17.0 weeks
Appeals lodged / allowed17 / 9—

All projects in Somerset

Is the status up to date?

32% of applications still shown as pending in REPD were submitted more than two years ago, and only 37% of pending records were updated in the last 12 months, so some of them may already have been decided. Near BS28, 1 project has a status that may be out of date (pending for over two years, or approved with a permission expiry date already passed). Check the council's planning register for the latest decision.