Energy Projects Near You

Solar, wind and battery projects near Glastonbury (BA6)

19 solar, wind or battery projects of 150 kW or more are recorded within 10 km of the centre of BA6 (Somerset): 2 are waiting for a planning decision, 3 approved but not yet running, 10 operational. The largest live scheme is Nythe Road, Pedwell Solar Photovoltaic Park (40 MW solar farm, application submitted on 22 July 2025, no decision recorded), 8.3 km away. Source: Renewable Energy Planning Database, July 2026 extract.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

19projects within 10 km
2awaiting a decision
3approved, not running
10operational

Projects within 10 km of BA6

Projects of 1 MW and more (16)

ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updatedCouncilkm
Middle Drove and Porchestall Drovesolar farmsolar farm1.2refusedupdated Oct 2025Jun 2025refused Oct 2025Oct 2025Somerset1.8
Norwood Park Farmsolar farmsolar farm7refused on appealupdated Feb 2016Aug 2013refused Oct 2014Feb 2016Somerset2.1
Park Wood Solar Farmsolar farmsolar farm5operationalupdated Jul 2012May 2011granted Jul 2011Jul 2012Somerset4.8
Whitley Farm (2 of 2)solar farmsolar farm3.5operationalupdated Jul 2018Jul 2013granted Oct 2013Jul 2018Somerset5.6
Whitley Farm (1 of 2)solar farmsolar farm3.5operationalupdated Jul 2018Jul 2013granted Oct 2013Jul 2018Somerset6.3
Higher Hill Farm (extension)solar farmsolar farm1.5operationalupdated Nov 2016May 2014granted Sep 2014Nov 2016Somerset7.0
Worminster Downsolar farmsolar farm15refused on appealupdated Oct 2015Jun 2014refused Aug 2014Oct 2015Somerset7.2
Higher Hill Farmsolar farmsolar farm5operationalupdated Oct 2012Mar 2011granted Jun 2011Oct 2012Somerset7.4
Nythe Road, Pedwell Solar Photovoltaic Parksolar farmsolar farm40application submittedupdated Aug 2025Jul 2025—Aug 2025Somerset8.3
Redlands Farmsolar farmsolar farm6.2operationalupdated Jun 2015Jun 2013granted Nov 2013Jun 2015Somerset8.4
Charlie Bighams Quarry Kitchen, Dulcote Hill Lanesolar farmsolar farm2.2approved, not builtupdated Oct 2025Nov 2024granted Sep 2025Oct 2025Somerset8.5
Somerton Door Farm, Somerton Door Drove Solar farmsolar farmsolar farm20application submittedupdated Sep 2025Jul 2025—Sep 2025Somerset9.0
Somerton Door Farmsolar farmsolar farm8.7operationalupdated May 2015Mar 2014granted Jun 2014May 2015Somerset9.0
Little Park Farmsolar farmsolar farm8.6application withdrawnupdated Feb 2013Dec 2012—Feb 2013Somerset9.3
Manor Farm (Keinton Mandeville)solar farmsolar farm1operationalupdated Mar 2013Mar 2011granted May 2011Mar 2013Somerset9.3
Hawkers Farmsolar farmsolar farm9.5operationalupdated Apr 2015Nov 2014granted Feb 2015Apr 2015Somerset10.0
Smaller schemes under 1 MW, mostly rooftop solar (3)
ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updatedCouncilkm
Whitley Solar Park, Ashcottbattery storagebattery storage—approved, not built may be out of dateupdated Apr 2022Mar 2022granted May 2022Apr 2022Somerset5.9
Higher Hill Farm Energy Storagebattery storagebattery storage0.3operationalupdated Mar 2017Mar 2011—Mar 2017Somerset7.0
Worthy Lane, Piltonrooftop solarrooftop solar0.2approved, not builtupdated May 2025Mar 2025granted Apr 2025May 2025Somerset8.7

Distance from the average position of the BA6 postcodes, not from your home. Projects of 5 MW and more have their own page with dates and planning history.

By type

TypeAllPendingApprovedOperationalRefusedMW in pipeline
Solar farm16219362.2
Rooftop solar101000.2
Battery storage201100

MW in pipeline: pending, approved and under-construction capacity.

How Somerset decides solar, wind and battery applications

ApplicationsSomersetUK
Decided applications (solar, wind, battery)18510,236
Refused46 (25%)19%
Solar refused34 of 15312%
Onshore wind refused9 of 1045%
Battery storage refused3 of 2216%
Median time from submission to decision14.0 weeks17.0 weeks
Appeals lodged / allowed17 / 9—

All projects in Somerset

Is the status up to date?

32% of applications still shown as pending in REPD were submitted more than two years ago, and only 37% of pending records were updated in the last 12 months, so some of them may already have been decided. Near BA6, 1 project has a status that may be out of date (pending for over two years, or approved with a permission expiry date already passed). Check the council's planning register for the latest decision.