Energy Projects Near You

Park Wood Solar Farm (5 MW)

Park Wood Solar Farm is a 5 MW solar farm project in Somerset, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: operational since 29 September 2011; the record was last updated on 13 July 2012.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

5 MWsolar farm
operationalstatus in REPD
13 July 2012record last updated
Somersetcouncil area

Planning timeline

DateStage
4 May 2011Application submitted
28 July 2011Planning permission granted
29 September 2011Operational

Project details

Technology
solar farm
Capacity
5 MW
Status (REPD)
operational
Record last updated
13 July 2012
Operator or applicant
Solar Power Generation Limited
Planning authority
Somerset
Planning application reference
2011/0781
Site area
12.8 ha
Address (REPD)
Park Wood, Butleigh, Glastonbury
Council area (by location)
Somerset
Time to decision
12 weeks
Name in REPD
PARK WOOD SOLAR FARM
REPD reference
1076

Who decides

ApplicationsSomersetUK
Decided applications (solar, wind, battery)18510,236
Refused46 (25%)19%
Solar refused34 of 15312%
Onshore wind refused9 of 1045%
Battery storage refused3 of 2216%
Median time from submission to decision14.0 weeks17.0 weeks
Appeals lodged / allowed17 / 9—

Other large projects within 10 km

ProjectTypeMWStatuskm
Higher Hill Farmsolar farm5operational3.4
Norwood Park Farmsolar farm7refused on appeal4.8
Somerton Door Farm, Somerton Door Drove Solar farmsolar farm20application submitted7.2
Somerton Door Farmsolar farm8.7operational7.2
Little Park Farmsolar farm8.6application withdrawn7.9
Worminster Downsolar farm15refused on appeal9.3

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (51.1052, -2.6728).