Energy Projects Near You

Worminster Down (15 MW solar farm)

Worminster Down is a 15 MW solar farm project in Somerset, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: refused on appeal on 28 August 2015; the record was last updated on 5 October 2015.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

15 MWsolar farm
refused on appealstatus in REPD
5 October 2015record last updated
Somersetcouncil area

Planning timeline

DateStage
10 June 2014Application submitted
19 August 2014Refused by the planning authority
18 March 2015Appeal lodged
28 August 2015Appeal refused

Project details

Technology
solar farm
Capacity
15 MW
Status (REPD)
refused on appeal
Record last updated
5 October 2015
Operator or applicant
Good Energy Generation
Planning authority
Somerset
Planning application reference
2014/0962/FUL
Appeal reference
APP/Q3305/W/15/3003992
Site area
46.1 ha
Address (REPD)
Worminster Down Cross Farm North Wootton
Council area (by location)
Somerset
Time to decision
10 weeks
REPD reference
2317

Who decides

ApplicationsSomersetUK
Decided applications (solar, wind, battery)18510,236
Refused46 (25%)19%
Solar refused34 of 15312%
Onshore wind refused9 of 1045%
Battery storage refused3 of 2216%
Median time from submission to decision14.0 weeks17.0 weeks
Appeals lodged / allowed17 / 9—

Other large projects within 10 km

ProjectTypeMWStatuskm
Crapnell Farm Solar Farmsolar farm5.4operational4.5
Norwood Park Farmsolar farm7refused on appeal5.3
Pylle Southern solar park (Lower Easton Farm)solar farm5operational7.6
Lower Easton Farmsolar farm13.5refused7.6
Hurlingpot Farmsolar farm5.3refused on appeal8.0
The Royal Bath & West Showground Solar Farmsolar farm5abandoned8.4
Shooters Bottom Solar Parksolar farm7operational8.8
Lodge Farm Solar Farmsolar farm5under construction9.0
Park Wood Solar Farmsolar farm5operational9.3

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (51.1843, -2.63).