Lower Easton Farm (13.5 MW solar farm)

Lower Easton Farm is a 13.5 MW solar farm project in Somerset, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: refused on 16 October 2014; the record was last updated on 7 November 2014.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

13.5 MWsolar farm
refusedstatus in REPD
7 November 2014record last updated
Somersetcouncil area

Planning timeline

DateStage
20 June 2014Application submitted
16 October 2014Refused by the planning authority

Project details

Technology
solar farm
Capacity
13.5 MW
Status (REPD)
refused
Record last updated
7 November 2014
Operator or applicant
Pylle Solar
Planning authority
Somerset
Planning application reference
2014/1174/FUL
Site area
25.0 ha
Address (REPD)
Land Off Easton Lane, Pylle, Somerset
Council area (by location)
Somerset
Time to decision
17 weeks
REPD reference
1849

Who decides

ApplicationsSomersetUK
Decided applications (solar, wind, battery)18510,236
Refused46 (25%)19%
Solar refused34 of 15312%
Onshore wind refused9 of 1045%
Battery storage refused3 of 2216%
Median time from submission to decision14.0 weeks17.0 weeks
Appeals lodged / allowed17 / 9—

Other large projects within 10 km

ProjectTypeMWStatuskm
Pylle Southern solar park (Lower Easton Farm)solar farm5operational<0.1
The Royal Bath & West Showground Solar Farmsolar farm5abandoned1.2
Hurlingpot Farmsolar farm5.3refused on appeal5.2
Lodge Farm Solar Farmsolar farm5under construction6.9
Crapnell Farm Solar Farmsolar farm5.4operational7.5
Worminster Downsolar farm15refused on appeal7.6
Sheephouse Farm solar parksolar farm9refused7.9
Norwood Park Farmsolar farm7refused on appeal9.8

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (51.1463, -2.5395).