Sheephouse Farm solar park (9 MW)

Sheephouse Farm solar park is a 9 MW solar farm project in Somerset, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: refused on 16 August 2013; the record was last updated on 4 September 2013.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

9 MWsolar farm
refusedstatus in REPD
4 September 2013record last updated
Somersetcouncil area

Planning timeline

DateStage
21 May 2013Application submitted
16 August 2013Refused by the planning authority

Project details

Technology
solar farm
Capacity
9 MW
Status (REPD)
refused
Record last updated
4 September 2013
Operator or applicant
Esconrg Ltd
Planning authority
Somerset
Planning application reference
13/01668/FUL
Address (REPD)
Land OS 3969 Brewham Road Bruton Somerset
Council area (by location)
Somerset
Time to decision
12 weeks
REPD reference
1130

Who decides

ApplicationsSomersetUK
Decided applications (solar, wind, battery)18510,236
Refused46 (25%)19%
Solar refused34 of 15312%
Onshore wind refused9 of 1045%
Battery storage refused3 of 2216%
Median time from submission to decision14.0 weeks17.0 weeks
Appeals lodged / allowed17 / 9—

Other large projects within 10 km

ProjectTypeMWStatuskm
The Royal Bath & West Showground Solar Farmsolar farm5abandoned7.0
Hook Valley Solar Parksolar farm17operational7.7
Pylle Southern solar park (Lower Easton Farm)solar farm5operational7.9
Lower Easton Farmsolar farm13.5refused7.9
Brains Solar Farmsolar farm18.8approved, not built8.9
Clapton Farm Solar Parksolar farm5operational9.2
Holwell Hillsolar farm6operational9.6
Land at Sutor Farmsolar farm5operational9.7
Hurlingpot Farmsolar farm5.3refused on appeal9.8

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (51.1183, -2.4361).