Hook Valley Solar Park (17 MW)

Hook Valley Solar Park is a 17 MW solar farm project in Somerset, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: operational since 31 March 2014; the record was last updated on 26 August 2014.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

17 MWsolar farm
operationalstatus in REPD
26 August 2014record last updated
Somersetcouncil area

Planning timeline

DateStage
21 November 2012Application submitted
20 February 2013Refused by the planning authority
26 September 2013Planning permission granted
26 September 2013Appeal allowed
31 March 2014Operational

Project details

Technology
solar farm
Capacity
17 MW
Status (REPD)
operational
Record last updated
26 August 2014
Operator or applicant
British Solar Renewables (formerly know as Solar Power Generation)
Planning authority
Somerset
Planning application reference
12/04445/FUL
Appeal reference
12/04445/FUL
Site area
31.0 ha
Address (REPD)
Lawrence Hill, Wincanton, Somerset, BA9 8AD
Council area (by location)
Somerset
Time to decision
44 weeks
REPD reference
2005

Who decides

ApplicationsSomersetUK
Decided applications (solar, wind, battery)18510,236
Refused46 (25%)19%
Solar refused34 of 15312%
Onshore wind refused9 of 1045%
Battery storage refused3 of 2216%
Median time from submission to decision14.0 weeks17.0 weeks
Appeals lodged / allowed17 / 9—

Other large projects within 10 km

ProjectTypeMWStatuskm
Brains Solar Farmsolar farm18.8approved, not built2.6
Land at Sutor Farmsolar farm5operational3.3
Clapton Farm Solar Parksolar farm5operational6.2
Land at Bowden Lanesolar farm5operational7.4
Sheephouse Farm solar parksolar farm9refused7.7
Manor Farm (Dorset)solar farm5operational8.2
Silton Wind Farmwind farm10refused on appeal8.9
Land at Stalbridge Parksolar farm5operational9.3
Sutton Montis Road Solar Park / Sutton Bridge Solar Farmsolar farm5.4operational9.9

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (51.0486, -2.4349).