Sutton Montis Road Solar Park / Sutton Bridge Solar Farm (5.4 MW)

Sutton Montis Road Solar Park / Sutton Bridge Solar Farm is a 5.4 MW solar farm project in Somerset, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: operational since 10 February 2015; the record was last updated on 18 May 2015.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

5.4 MWsolar farm
operationalstatus in REPD
18 May 2015record last updated
Somersetcouncil area

Planning timeline

DateStage
29 April 2013Application submitted
28 January 2014Planning permission granted
1 September 2014Construction started
10 February 2015Operational

Project details

Technology
solar farm
Capacity
5.4 MW
Status (REPD)
operational
Record last updated
18 May 2015
Operator or applicant
PS Renewables
Planning authority
Somerset
Planning application reference
13/01697/FUL
Site area
12.7 ha
Address (REPD)
Land OS 4200, Sutton Montis Road, Queen Camel, Yeovil
Council area (by location)
Somerset
Time to decision
39 weeks
REPD reference
2067

Who decides

ApplicationsSomersetUK
Decided applications (solar, wind, battery)18510,236
Refused46 (25%)19%
Solar refused34 of 15312%
Onshore wind refused9 of 1045%
Battery storage refused3 of 2216%
Median time from submission to decision14.0 weeks17.0 weeks
Appeals lodged / allowed17 / 9—

Other large projects within 10 km

ProjectTypeMWStatuskm
Bindwell Lanesolar farm13.4permission expired0.5
Southfield Farm Solar Parksolar farm11.5operational3.1
Chilton Cantelo Solar Farmsolar farm5operational3.4
Hook Valley Solar Parksolar farm17operational9.9

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (51.0133, -2.5647).