Solar, wind and battery projects near Sherborne (DT9)
18 solar, wind or battery projects of 150 kW or more are recorded within 10 km of the centre of DT9 (Dorset): 2 are waiting for a planning decision, 3 approved but not yet running, 9 operational. The largest live scheme is Caswell Farm, Common Lane Solar Farm (40 MW solar farm, application submitted on 19 August 2025, no decision recorded), 7.9 km away. Source: Renewable Energy Planning Database, July 2026 extract.
Projects within 10 km of DT9
Projects of 1 MW and more (12)
| Project | Type | MW | Status (REPD) | Submitted | Decision | Record updated | Council | km |
|---|---|---|---|---|---|---|---|---|
| Higher Stockbridge Farmsolar farm | solar farm | 35 | approved, not built may be out of dateupdated Sep 2023 | Dec 2019 | granted Dec 2021 | Sep 2023 | Dorset | 4.8 |
| Milborne Port Solar Farmsolar farm | solar farm | 4.2 | operationalupdated Jun 2018 | May 2015 | granted Aug 2016 | Jun 2018 | Somerset | 5.7 |
| Clifton Farmsolar farm | solar farm | 35 | operationalupdated Nov 2025 | May 2020 | granted May 2021 | Nov 2025 | Dorset | 7.0 |
| Alton Mead Lanesolar farm | solar farm | 5 | permission expiredupdated Jan 2020 | Sep 2015 | granted Jan 2016 | Jan 2020 | Dorset | 7.4 |
| Land at Bowden Lanesolar farm | solar farm | 5 | operationalupdated Jun 2017 | Jun 2015 | granted Oct 2015 | Jun 2017 | Somerset | 7.6 |
| Caswell Farm, Common Lane Solar Farmsolar farm | solar farm | 40 | application submittedupdated Oct 2025 | Aug 2025 | — | Oct 2025 | Dorset | 7.9 |
| Caswell Farm, Common Lanebattery storage | battery storage | 20 | application submittedupdated Oct 2025 | Aug 2025 | — | Oct 2025 | Dorset | 7.9 |
| Caswell Farm Solar Parksolar farm | solar farm | 6.7 | operationalupdated Aug 2016 | Mar 2013 | granted Dec 2013 | Aug 2016 | Dorset | 8.2 |
| Chilton Cantelo Solar Farmsolar farm | solar farm | 5 | operationalupdated Jul 2018 | Mar 2012 | granted Jul 2012 | Jul 2018 | Somerset | 8.4 |
| Sutton Montis Road Solar Park / Sutton Bridge Solar Farmsolar farm | solar farm | 5.4 | operationalupdated May 2015 | Apr 2013 | granted Jan 2014 | May 2015 | Somerset | 8.6 |
| Bindwell Lanesolar farm | solar farm | 13.4 | permission expiredupdated Feb 2021 | Mar 2020 | granted Jan 2021 | Feb 2021 | Somerset | 9.0 |
| Land at Stalbridge Parksolar farm | solar farm | 5 | operationalupdated Jun 2017 | Jul 2015 | granted Oct 2015 | Jun 2017 | Dorset | 10.0 |
Smaller schemes under 1 MW, mostly rooftop solar (6)
| Project | Type | MW | Status (REPD) | Submitted | Decision | Record updated | Council | km |
|---|---|---|---|---|---|---|---|---|
| Vale Road Sludge Treatment Works, Lyde Lanesolar farm | solar farm | — | approved, not builtupdated Nov 2023 | Oct 2023 | granted Nov 2023 | Nov 2023 | Somerset | 6.3 |
| Oxford Roadbattery storage | battery storage | — | permission expiredupdated Jun 2020 | Sep 2016 | — | Jun 2020 | Somerset | 6.3 |
| Tesco Queensway Placerooftop solar | rooftop solar | 0.3 | operationalupdated Dec 2019 | Jan 2019 | — | Dec 2019 | Somerset | 8.5 |
| Ilchester Road - Micro Energy Storage Facilitybattery storage | battery storage | 0.2 | approved, not builtupdated Aug 2024 | May 2024 | granted Jul 2024 | Aug 2024 | Somerset | 8.6 |
| Morrisons, Lysander Roadrooftop solar | rooftop solar | 0.4 | refusedupdated May 2024 | Jan 2024 | refused Apr 2024 | May 2024 | Somerset | 9.3 |
| Westland Leisure Complexrooftop solar | rooftop solar | 0.2 | operationalupdated Jun 2021 | May 2021 | granted Aug 2021 | Jun 2021 | Somerset | 9.3 |
Distance from the average position of the DT9 postcodes, not from your home. Projects of 5 MW and more have their own page with dates and planning history.
By type
| Type | All | Pending | Approved | Operational | Refused | MW in pipeline |
|---|---|---|---|---|---|---|
| Solar farm | 12 | 1 | 2 | 7 | 0 | 75 |
| Rooftop solar | 3 | 0 | 0 | 2 | 1 | 0 |
| Battery storage | 3 | 1 | 1 | 0 | 0 | 20.2 |
MW in pipeline: pending, approved and under-construction capacity.
How Dorset decides solar, wind and battery applications
| Applications | Dorset | UK |
|---|---|---|
| Decided applications (solar, wind, battery) | 125 | 10,236 |
| Refused | 23 (18%) | 19% |
| Solar refused | 15 of 105 | 12% |
| Onshore wind refused | 5 of 5 | 45% |
| Battery storage refused | 3 of 15 | 16% |
| Median time from submission to decision | 19.0 weeks | 17.0 weeks |
| Appeals lodged / allowed | 6 / 6 | — |
Is the status up to date?
32% of applications still shown as pending in REPD were submitted more than two years ago, and only 37% of pending records were updated in the last 12 months, so some of them may already have been decided. Near DT9, 1 project has a status that may be out of date (pending for over two years, or approved with a permission expiry date already passed). Check the council's planning register for the latest decision.