Solar, wind and battery projects near Yeovil (BA20)
18 solar, wind or battery projects of 150 kW or more are recorded within 10 km of the centre of BA20 (Somerset): 2 are waiting for a planning decision, 6 approved but not yet running, 6 operational. The largest live scheme is Caswell Farm, Common Lane Solar Farm (40 MW solar farm, application submitted on 19 August 2025, no decision recorded), 7.0 km away. Source: Renewable Energy Planning Database, July 2026 extract.
Projects within 10 km of BA20
Projects of 1 MW and more (9)
| Project | Type | MW | Status (REPD) | Submitted | Decision | Record updated | Council | km |
|---|---|---|---|---|---|---|---|---|
| Camp Road, West Cokersolar farm | solar farm | 15.2 | approved, not builtupdated Jul 2025 | Aug 2023 | granted Jan 2024 | Jul 2025 | Somerset | 3.1 |
| Clifton Farmsolar farm | solar farm | 35 | operationalupdated Nov 2025 | May 2020 | granted May 2021 | Nov 2025 | Dorset | 4.6 |
| Caswell Farm Solar Parksolar farm | solar farm | 6.7 | operationalupdated Aug 2016 | Mar 2013 | granted Dec 2013 | Aug 2016 | Dorset | 6.6 |
| Chilton Cantelo Solar Farmsolar farm | solar farm | 5 | operationalupdated Jul 2018 | Mar 2012 | granted Jul 2012 | Jul 2018 | Somerset | 7.0 |
| Caswell Farm, Common Lane Solar Farmsolar farm | solar farm | 40 | application submittedupdated Oct 2025 | Aug 2025 | — | Oct 2025 | Dorset | 7.0 |
| Caswell Farm, Common Lanebattery storage | battery storage | 20 | application submittedupdated Oct 2025 | Aug 2025 | — | Oct 2025 | Dorset | 7.0 |
| Tintinhull Forts Solar Parksolar farm | solar farm | 6 | refusedupdated Nov 2013 | Jul 2013 | refused Oct 2013 | Nov 2013 | Somerset | 8.7 |
| Southfield Farm Solar Parksolar farm | solar farm | 11.5 | operationalupdated Jul 2016 | Jan 2014 | granted Jul 2015 | Jul 2016 | Somerset | 8.9 |
| Alton Mead Lanesolar farm | solar farm | 5 | permission expiredupdated Jan 2020 | Sep 2015 | granted Jan 2016 | Jan 2020 | Dorset | 8.9 |
Smaller schemes under 1 MW, mostly rooftop solar (9)
| Project | Type | MW | Status (REPD) | Submitted | Decision | Record updated | Council | km |
|---|---|---|---|---|---|---|---|---|
| Morrisons, Lysander Roadrooftop solar | rooftop solar | 0.4 | refusedupdated May 2024 | Jan 2024 | refused Apr 2024 | May 2024 | Somerset | 0.4 |
| Westland Leisure Complexrooftop solar | rooftop solar | 0.2 | operationalupdated Jun 2021 | May 2021 | granted Aug 2021 | Jun 2021 | Somerset | 0.5 |
| Tesco Queensway Placerooftop solar | rooftop solar | 0.3 | operationalupdated Dec 2019 | Jan 2019 | — | Dec 2019 | Somerset | 0.8 |
| Ilchester Road - Micro Energy Storage Facilitybattery storage | battery storage | 0.2 | approved, not builtupdated Aug 2024 | May 2024 | granted Jul 2024 | Aug 2024 | Somerset | 1.1 |
| Bunford Park, Plot 1Bbattery storage | battery storage | — | approved, not builtupdated Jul 2024 | Oct 2023 | granted Jun 2024 | Jul 2024 | Somerset | 1.9 |
| Vale Road Sludge Treatment Works, Lyde Lanesolar farm | solar farm | — | approved, not builtupdated Nov 2023 | Oct 2023 | granted Nov 2023 | Nov 2023 | Somerset | 3.0 |
| Camp Road, West Cokerbattery storage | battery storage | — | approved, not builtupdated Jul 2025 | Aug 2023 | granted Jan 2024 | Jul 2025 | Somerset | 3.1 |
| Oxford Roadbattery storage | battery storage | — | permission expiredupdated Jun 2020 | Sep 2016 | — | Jun 2020 | Somerset | 3.2 |
| Cobham Hall Fleet Air Arm Museum, Rnas Yeovilton Roadrooftop solar | rooftop solar | 0.2 | approved, not builtupdated Jul 2024 | Jan 2024 | granted Jun 2024 | Jul 2024 | Somerset | 8.6 |
Distance from the average position of the BA20 postcodes, not from your home. Projects of 5 MW and more have their own page with dates and planning history.
By type
| Type | All | Pending | Approved | Operational | Refused | MW in pipeline |
|---|---|---|---|---|---|---|
| Solar farm | 9 | 1 | 2 | 4 | 1 | 55.2 |
| Rooftop solar | 4 | 0 | 1 | 2 | 1 | 0.2 |
| Battery storage | 5 | 1 | 3 | 0 | 0 | 20.2 |
MW in pipeline: pending, approved and under-construction capacity.
How Somerset decides solar, wind and battery applications
| Applications | Somerset | UK |
|---|---|---|
| Decided applications (solar, wind, battery) | 185 | 10,236 |
| Refused | 46 (25%) | 19% |
| Solar refused | 34 of 153 | 12% |
| Onshore wind refused | 9 of 10 | 45% |
| Battery storage refused | 3 of 22 | 16% |
| Median time from submission to decision | 14.0 weeks | 17.0 weeks |
| Appeals lodged / allowed | 17 / 9 | — |
Is the status up to date?
32% of applications still shown as pending in REPD were submitted more than two years ago, and only 37% of pending records were updated in the last 12 months, so some of them may already have been decided. Check the council's planning register for the latest decision.