Energy Projects Near You

Solar, wind and battery projects near Martock (TA12)

16 solar, wind or battery projects of 150 kW or more are recorded within 10 km of the centre of TA12 (Somerset): 6 approved but not yet running, 4 operational. The largest live scheme is Camp Road, West Coker (15.2 MW solar farm, approved on 31 January 2024, not yet built), 8.3 km away. Source: Renewable Energy Planning Database, July 2026 extract.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

16projects within 10 km
0awaiting a decision
6approved, not running
4operational

Projects within 10 km of TA12

Projects of 1 MW and more (8)

ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updatedCouncilkm
Tintinhull Forts Solar Parksolar farmsolar farm6refusedupdated Nov 2013Jul 2013refused Oct 2013Nov 2013Somerset4.4
Tengore Lanesolar farmsolar farm3.6operationalupdated Sep 2018Aug 2013granted Jun 2014Sep 2018Somerset7.7
Hurcott Copse Solar Farmsolar farmsolar farm10operationalupdated Apr 2015Jul 2014granted Sep 2014Apr 2015Somerset7.7
Camp Road, West Cokersolar farmsolar farm15.2approved, not builtupdated Jul 2025Aug 2023granted Jan 2024Jul 2025Somerset8.3
Lower Severalls Farmsolar farmsolar farm10.8operationalupdated Oct 2017Jul 2014granted Sep 2014Oct 2017Somerset8.5
Bushfurlong Solar Farmsolar farmsolar farm5application withdrawnupdated Jan 2012Feb 2011—Jan 2012Somerset8.5
Langport Farmsolar farmsolar farm5application withdrawnupdated Feb 2012——Feb 2012Somerset8.9
Caves Farm Solar Parksolar farmsolar farm4.8refusedupdated Jun 2013Feb 2013refused May 2013Jun 2013Somerset9.0
Smaller schemes under 1 MW, mostly rooftop solar (8)
ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updatedCouncilkm
ADM Protexin, Lopen Headrooftop solarrooftop solar0.2approved, not built may be out of dateupdated Nov 2022Aug 2022granted Sep 2022Nov 2022Somerset5.7
Adm Protexin, Lopen Headrooftop solarrooftop solar—approved, not builtupdated Aug 2025May 2025granted Jun 2025Aug 2025Somerset5.7
Long Sutton - Renewable Energy Buildingrooftop solarrooftop solar—application withdrawnupdated May 2022May 2022—May 2022Somerset6.0
Camp Road, West Cokerbattery storagebattery storage—approved, not builtupdated Jul 2025Aug 2023granted Jan 2024Jul 2025Somerset8.3
Bunford Park, Plot 1Bbattery storagebattery storage—approved, not builtupdated Jul 2024Oct 2023granted Jun 2024Jul 2024Somerset8.7
Westland Leisure Complexrooftop solarrooftop solar0.2operationalupdated Jun 2021May 2021granted Aug 2021Jun 2021Somerset9.4
Morrisons, Lysander Roadrooftop solarrooftop solar0.4refusedupdated May 2024Jan 2024refused Apr 2024May 2024Somerset9.8
Ilchester Road - Micro Energy Storage Facilitybattery storagebattery storage0.2approved, not builtupdated Aug 2024May 2024granted Jul 2024Aug 2024Somerset10.0

Distance from the average position of the TA12 postcodes, not from your home. Projects of 5 MW and more have their own page with dates and planning history.

By type

TypeAllPendingApprovedOperationalRefusedMW in pipeline
Solar farm8013215.2
Rooftop solar502110.2
Battery storage303000.2

MW in pipeline: pending, approved and under-construction capacity.

How Somerset decides solar, wind and battery applications

ApplicationsSomersetUK
Decided applications (solar, wind, battery)18510,236
Refused46 (25%)19%
Solar refused34 of 15312%
Onshore wind refused9 of 1045%
Battery storage refused3 of 2216%
Median time from submission to decision14.0 weeks17.0 weeks
Appeals lodged / allowed17 / 9—

All projects in Somerset

Is the status up to date?

32% of applications still shown as pending in REPD were submitted more than two years ago, and only 37% of pending records were updated in the last 12 months, so some of them may already have been decided. Near TA12, 1 project has a status that may be out of date (pending for over two years, or approved with a permission expiry date already passed). Check the council's planning register for the latest decision.