Solar, wind and battery projects near Montacute (TA15)
19 solar, wind or battery projects of 150 kW or more are recorded within 10 km of the centre of TA15 (Somerset): 10 approved but not yet running, 5 operational. The largest live scheme is Solar Farm at Pipplepen Farm Solar Park (32 MW solar farm, approved on 24 January 2023, not yet built; REPD status may be out of date), 9.8 km away. Source: Renewable Energy Planning Database, July 2026 extract.
Projects within 10 km of TA15
Projects of 1 MW and more (6)
| Project | Type | MW | Status (REPD) | Submitted | Decision | Record updated | Council | km |
|---|---|---|---|---|---|---|---|---|
| Camp Road, West Cokersolar farm | solar farm | 15.2 | approved, not builtupdated Jul 2025 | Aug 2023 | granted Jan 2024 | Jul 2025 | Somerset | 3.7 |
| Tintinhull Forts Solar Parksolar farm | solar farm | 6 | refusedupdated Nov 2013 | Jul 2013 | refused Oct 2013 | Nov 2013 | Somerset | 5.3 |
| Lower Severalls Farmsolar farm | solar farm | 10.8 | operationalupdated Oct 2017 | Jul 2014 | granted Sep 2014 | Oct 2017 | Somerset | 7.2 |
| Chilton Cantelo Solar Farmsolar farm | solar farm | 5 | operationalupdated Jul 2018 | Mar 2012 | granted Jul 2012 | Jul 2018 | Somerset | 9.3 |
| Clifton Farmsolar farm | solar farm | 35 | operationalupdated Nov 2025 | May 2020 | granted May 2021 | Nov 2025 | Dorset | 9.5 |
| Solar Farm at Pipplepen Farm Solar Parksolar farm | solar farm | 32 | approved, not built may be out of dateupdated Aug 2021 | Aug 2021 | granted Jan 2023 | Aug 2021 | Dorset | 9.8 |
Smaller schemes under 1 MW, mostly rooftop solar (13)
| Project | Type | MW | Status (REPD) | Submitted | Decision | Record updated | Council | km |
|---|---|---|---|---|---|---|---|---|
| Camp Road, West Cokerbattery storage | battery storage | — | approved, not builtupdated Jul 2025 | Aug 2023 | granted Jan 2024 | Jul 2025 | Somerset | 3.7 |
| Bunford Park, Plot 1Bbattery storage | battery storage | — | approved, not builtupdated Jul 2024 | Oct 2023 | granted Jun 2024 | Jul 2024 | Somerset | 3.9 |
| Westland Leisure Complexrooftop solar | rooftop solar | 0.2 | operationalupdated Jun 2021 | May 2021 | granted Aug 2021 | Jun 2021 | Somerset | 4.9 |
| Morrisons, Lysander Roadrooftop solar | rooftop solar | 0.4 | refusedupdated May 2024 | Jan 2024 | refused Apr 2024 | May 2024 | Somerset | 5.1 |
| Ilchester Road - Micro Energy Storage Facilitybattery storage | battery storage | 0.2 | approved, not builtupdated Aug 2024 | May 2024 | granted Jul 2024 | Aug 2024 | Somerset | 5.5 |
| Tesco Queensway Placerooftop solar | rooftop solar | 0.3 | operationalupdated Dec 2019 | Jan 2019 | — | Dec 2019 | Somerset | 5.7 |
| ADM Protexin, Lopen Headrooftop solar | rooftop solar | 0.2 | approved, not built may be out of dateupdated Nov 2022 | Aug 2022 | granted Sep 2022 | Nov 2022 | Somerset | 7.5 |
| Adm Protexin, Lopen Headrooftop solar | rooftop solar | — | approved, not builtupdated Aug 2025 | May 2025 | granted Jun 2025 | Aug 2025 | Somerset | 7.5 |
| Vale Road Sludge Treatment Works, Lyde Lanesolar farm | solar farm | — | approved, not builtupdated Nov 2023 | Oct 2023 | granted Nov 2023 | Nov 2023 | Somerset | 7.9 |
| Oxford Roadbattery storage | battery storage | — | permission expiredupdated Jun 2020 | Sep 2016 | — | Jun 2020 | Somerset | 7.9 |
| Crewkerne Sewage Treatment Works, Blacknell Lanesolar farm | solar farm | — | approved, not builtupdated Aug 2023 | Apr 2023 | granted May 2023 | Aug 2023 | Somerset | 8.8 |
| Cobham Hall Fleet Air Arm Museum, Rnas Yeovilton Roadrooftop solar | rooftop solar | 0.2 | approved, not builtupdated Jul 2024 | Jan 2024 | granted Jun 2024 | Jul 2024 | Somerset | 9.0 |
| Long Sutton - Renewable Energy Buildingrooftop solar | rooftop solar | — | application withdrawnupdated May 2022 | May 2022 | — | May 2022 | Somerset | 9.1 |
Distance from the average position of the TA15 postcodes, not from your home. Projects of 5 MW and more have their own page with dates and planning history.
By type
| Type | All | Pending | Approved | Operational | Refused | MW in pipeline |
|---|---|---|---|---|---|---|
| Solar farm | 8 | 0 | 4 | 3 | 1 | 47.2 |
| Rooftop solar | 7 | 0 | 3 | 2 | 1 | 0.4 |
| Battery storage | 4 | 0 | 3 | 0 | 0 | 0.2 |
MW in pipeline: pending, approved and under-construction capacity.
How Somerset decides solar, wind and battery applications
| Applications | Somerset | UK |
|---|---|---|
| Decided applications (solar, wind, battery) | 185 | 10,236 |
| Refused | 46 (25%) | 19% |
| Solar refused | 34 of 153 | 12% |
| Onshore wind refused | 9 of 10 | 45% |
| Battery storage refused | 3 of 22 | 16% |
| Median time from submission to decision | 14.0 weeks | 17.0 weeks |
| Appeals lodged / allowed | 17 / 9 | — |
Is the status up to date?
32% of applications still shown as pending in REPD were submitted more than two years ago, and only 37% of pending records were updated in the last 12 months, so some of them may already have been decided. Near TA15, 2 projects have a status that may be out of date (pending for over two years, or approved with a permission expiry date already passed). Check the council's planning register for the latest decision.