Lower Severalls Farm (10.8 MW solar farm)

Lower Severalls Farm is a 10.8 MW solar farm project in Somerset, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: operational since 18 October 2017; the record was last updated on 18 October 2017.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

10.8 MWsolar farm
operationalstatus in REPD
18 October 2017record last updated
Somersetcouncil area

Planning timeline

DateStage
15 July 2014Application submitted
19 September 2014Planning permission granted
5 October 2015Construction started
18 October 2017Operational

Project details

Technology
solar farm
Capacity
10.8 MW
Status (REPD)
operational
Record last updated
18 October 2017
Operator or applicant
Sigma Solar Limited / OPDE
Planning authority
Somerset
Planning application reference
14/03128/FUL
Site area
21.8 ha
Address (REPD)
Land Adjacent Lower Severalls Farm, Lower Severalls Farm Road ,Crewkerne, Somerset
Council area (by location)
Somerset
Time to decision
9 weeks
REPD reference
2154

Who decides

ApplicationsSomersetUK
Decided applications (solar, wind, battery)18510,236
Refused46 (25%)19%
Solar refused34 of 15312%
Onshore wind refused9 of 1045%
Battery storage refused3 of 2216%
Median time from submission to decision14.0 weeks17.0 weeks
Appeals lodged / allowed17 / 9—

Other large projects within 10 km

ProjectTypeMWStatuskm
Solar Farm at Pipplepen Farm Solar Parksolar farm32approved, not built4.1
Mahe Farm, Dunsham Lanesolar farm18.5refused6.1
Camp Road, West Cokersolar farm15.2approved, not built7.1
Hurcott Copse Solar Farmsolar farm10operational7.5
Parsonage Barn (extension)solar farm7.6operational9.7

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (50.8989, -2.7772).