Solar, wind and battery projects near Merriott (TA16)
20 solar, wind or battery projects of 150 kW or more are recorded within 10 km of the centre of TA16 (Somerset): 10 approved but not yet running, 6 operational. The largest live scheme is Solar Farm at Pipplepen Farm Solar Park (32 MW solar farm, approved on 24 January 2023, not yet built; REPD status may be out of date), 5.7 km away. Source: Renewable Energy Planning Database, July 2026 extract.
Projects within 10 km of TA16
Projects of 1 MW and more (13)
| Project | Type | MW | Status (REPD) | Submitted | Decision | Record updated | Council | km |
|---|---|---|---|---|---|---|---|---|
| Lower Severalls Farmsolar farm | solar farm | 10.8 | operationalupdated Oct 2017 | Jul 2014 | granted Sep 2014 | Oct 2017 | Somerset | 1.7 |
| Lower Coombe Farm Solarsolar farm | solar farm | 1 | operationalupdated Aug 2011 | Nov 2010 | granted Jan 2011 | Aug 2011 | Somerset | 3.7 |
| Lower Coombe Farm (Bean Field)solar farm | solar farm | 1 | operationalupdated May 2013 | Jun 2012 | granted Aug 2012 | May 2013 | Somerset | 4.3 |
| Coombe Farm, Bean Field Solar Arrayssolar farm | solar farm | 1.8 | approved, not builtupdated Oct 2024 | Jun 2024 | granted Sep 2024 | Oct 2024 | Somerset | 4.4 |
| Solar Farm at Pipplepen Farm Solar Parksolar farm | solar farm | 32 | approved, not built may be out of dateupdated Aug 2021 | Aug 2021 | granted Jan 2023 | Aug 2021 | Dorset | 5.7 |
| Pattemores Transport (Crewkern)solar farm | solar farm | 2.1 | under constructionupdated Dec 2021 | Feb 2020 | — | Dec 2021 | Somerset | 5.8 |
| Hurcott Copse Solar Farmsolar farm | solar farm | 10 | operationalupdated Apr 2015 | Jul 2014 | granted Sep 2014 | Apr 2015 | Somerset | 5.9 |
| Mahe Farm, Dunsham Lanesolar farm | solar farm | 18.5 | refusedupdated Jun 2026 | May 2024 | refused May 2026 | Jun 2026 | Somerset | 6.3 |
| Cricket St Thomaswind farm | wind farm | 3.9 | application withdrawnupdated Jun 2011 | — | — | Jun 2011 | Somerset | 7.9 |
| Camp Road, West Cokersolar farm | solar farm | 15.2 | approved, not builtupdated Jul 2025 | Aug 2023 | granted Jan 2024 | Jul 2025 | Somerset | 7.9 |
| Parsonage Barn (extension)solar farm | solar farm | 7.6 | operationalupdated Aug 2013 | Jul 2012 | granted Oct 2012 | Aug 2013 | Somerset | 8.1 |
| Goldenhaye Field Solar Farmsolar farm | solar farm | 2 | operationalupdated Jun 2013 | Apr 2011 | granted Aug 2011 | Jun 2013 | Somerset | 8.8 |
| Modus Furniture, Manor Farmrooftop solar | rooftop solar | 1 | approved, not builtupdated Mar 2023 | Dec 2022 | granted Jan 2023 | Mar 2023 | Somerset | 8.9 |
Smaller schemes under 1 MW, mostly rooftop solar (7)
| Project | Type | MW | Status (REPD) | Submitted | Decision | Record updated | Council | km |
|---|---|---|---|---|---|---|---|---|
| Crewkerne Sewage Treatment Works, Blacknell Lanesolar farm | solar farm | — | approved, not builtupdated Aug 2023 | Apr 2023 | granted May 2023 | Aug 2023 | Somerset | 3.0 |
| ADM Protexin, Lopen Headrooftop solar | rooftop solar | 0.2 | approved, not built may be out of dateupdated Nov 2022 | Aug 2022 | granted Sep 2022 | Nov 2022 | Somerset | 3.2 |
| Adm Protexin, Lopen Headrooftop solar | rooftop solar | — | approved, not builtupdated Aug 2025 | May 2025 | granted Jun 2025 | Aug 2025 | Somerset | 3.2 |
| Mahe Farm, Dunsham Lanebattery storage | battery storage | — | refusedupdated Jun 2026 | May 2024 | refused May 2026 | Jun 2026 | Somerset | 6.3 |
| Camp Road, West Cokerbattery storage | battery storage | — | approved, not builtupdated Jul 2025 | Aug 2023 | granted Jan 2024 | Jul 2025 | Somerset | 7.9 |
| Tesco Ilminsterrooftop solar | rooftop solar | 0.2 | refusedupdated Aug 2021 | Jun 2021 | refused Jul 2021 | Aug 2021 | Somerset | 8.4 |
| Bunford Park, Plot 1Bbattery storage | battery storage | — | approved, not builtupdated Jul 2024 | Oct 2023 | granted Jun 2024 | Jul 2024 | Somerset | 8.9 |
Distance from the average position of the TA16 postcodes, not from your home. Projects of 5 MW and more have their own page with dates and planning history.
By type
| Type | All | Pending | Approved | Operational | Refused | MW in pipeline |
|---|---|---|---|---|---|---|
| Solar farm | 12 | 0 | 5 | 6 | 1 | 51.1 |
| Rooftop solar | 4 | 0 | 3 | 0 | 1 | 1.2 |
| Wind farm | 1 | 0 | 0 | 0 | 0 | 0 |
| Battery storage | 3 | 0 | 2 | 0 | 1 | 0 |
MW in pipeline: pending, approved and under-construction capacity.
How Somerset decides solar, wind and battery applications
| Applications | Somerset | UK |
|---|---|---|
| Decided applications (solar, wind, battery) | 185 | 10,236 |
| Refused | 46 (25%) | 19% |
| Solar refused | 34 of 153 | 12% |
| Onshore wind refused | 9 of 10 | 45% |
| Battery storage refused | 3 of 22 | 16% |
| Median time from submission to decision | 14.0 weeks | 17.0 weeks |
| Appeals lodged / allowed | 17 / 9 | — |
Is the status up to date?
32% of applications still shown as pending in REPD were submitted more than two years ago, and only 37% of pending records were updated in the last 12 months, so some of them may already have been decided. Near TA16, 2 projects have a status that may be out of date (pending for over two years, or approved with a permission expiry date already passed). Check the council's planning register for the latest decision.