Energy Projects Near You

Solar, wind and battery projects near Crewkerne (TA18)

20 solar, wind or battery projects of 150 kW or more are recorded within 10 km of the centre of TA18 (Somerset): 10 approved but not yet running, 6 operational. The largest live scheme is Solar Farm at Pipplepen Farm Solar Park (32 MW solar farm, approved on 24 January 2023, not yet built; REPD status may be out of date), 3.2 km away. Source: Renewable Energy Planning Database, July 2026 extract.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

20projects within 10 km
0awaiting a decision
10approved, not running
6operational

Projects within 10 km of TA18

Projects of 1 MW and more (13)

ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updatedCouncilkm
Lower Severalls Farmsolar farmsolar farm10.8operationalupdated Oct 2017Jul 2014granted Sep 2014Oct 2017Somerset1.9
Pattemores Transport (Crewkern)solar farmsolar farm2.1under constructionupdated Dec 2021Feb 2020—Dec 2021Somerset2.9
Lower Coombe Farm Solarsolar farmsolar farm1operationalupdated Aug 2011Nov 2010granted Jan 2011Aug 2011Somerset3.1
Solar Farm at Pipplepen Farm Solar Parksolar farmsolar farm32approved, not built may be out of dateupdated Aug 2021Aug 2021granted Jan 2023Aug 2021Dorset3.2
Lower Coombe Farm (Bean Field)solar farmsolar farm1operationalupdated May 2013Jun 2012granted Aug 2012May 2013Somerset3.6
Coombe Farm, Bean Field Solar Arrayssolar farmsolar farm1.8approved, not builtupdated Oct 2024Jun 2024granted Sep 2024Oct 2024Somerset3.7
Mahe Farm, Dunsham Lanesolar farmsolar farm18.5refusedupdated Jun 2026May 2024refused May 2026Jun 2026Somerset4.4
Cricket St Thomaswind farmwind farm3.9application withdrawnupdated Jun 2011——Jun 2011Somerset7.3
Modus Furniture, Manor Farmrooftop solarrooftop solar1approved, not builtupdated Mar 2023Dec 2022granted Jan 2023Mar 2023Somerset8.2
Hurcott Copse Solar Farmsolar farmsolar farm10operationalupdated Apr 2015Jul 2014granted Sep 2014Apr 2015Somerset8.2
Goldenhaye Field Solar Farmsolar farmsolar farm2operationalupdated Jun 2013Apr 2011granted Aug 2011Jun 2013Somerset8.4
Camp Road, West Cokersolar farmsolar farm15.2approved, not builtupdated Jul 2025Aug 2023granted Jan 2024Jul 2025Somerset8.6
Parsonage Barn (extension)solar farmsolar farm7.6operationalupdated Aug 2013Jul 2012granted Oct 2012Aug 2013Somerset10.0
Smaller schemes under 1 MW, mostly rooftop solar (7)
ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updatedCouncilkm
Crewkerne Sewage Treatment Works, Blacknell Lanesolar farmsolar farm—approved, not builtupdated Aug 2023Apr 2023granted May 2023Aug 2023Somerset0.4
Mahe Farm, Dunsham Lanebattery storagebattery storage—refusedupdated Jun 2026May 2024refused May 2026Jun 2026Somerset4.4
ADM Protexin, Lopen Headrooftop solarrooftop solar0.2approved, not built may be out of dateupdated Nov 2022Aug 2022granted Sep 2022Nov 2022Somerset6.1
Adm Protexin, Lopen Headrooftop solarrooftop solar—approved, not builtupdated Aug 2025May 2025granted Jun 2025Aug 2025Somerset6.1
Camp Road, West Cokerbattery storagebattery storage—approved, not builtupdated Jul 2025Aug 2023granted Jan 2024Jul 2025Somerset8.6
Bunford Park, Plot 1Bbattery storagebattery storage—approved, not builtupdated Jul 2024Oct 2023granted Jun 2024Jul 2024Somerset9.7
Tesco Ilminsterrooftop solarrooftop solar0.2refusedupdated Aug 2021Jun 2021refused Jul 2021Aug 2021Somerset9.9

Distance from the average position of the TA18 postcodes, not from your home. Projects of 5 MW and more have their own page with dates and planning history.

By type

TypeAllPendingApprovedOperationalRefusedMW in pipeline
Solar farm12056151.1
Rooftop solar403011.2
Wind farm100000
Battery storage302010

MW in pipeline: pending, approved and under-construction capacity.

How Somerset decides solar, wind and battery applications

ApplicationsSomersetUK
Decided applications (solar, wind, battery)18510,236
Refused46 (25%)19%
Solar refused34 of 15312%
Onshore wind refused9 of 1045%
Battery storage refused3 of 2216%
Median time from submission to decision14.0 weeks17.0 weeks
Appeals lodged / allowed17 / 9—

All projects in Somerset

Is the status up to date?

32% of applications still shown as pending in REPD were submitted more than two years ago, and only 37% of pending records were updated in the last 12 months, so some of them may already have been decided. Near TA18, 2 projects have a status that may be out of date (pending for over two years, or approved with a permission expiry date already passed). Check the council's planning register for the latest decision.